Snowy Hydro boss apologises for cost blowouts, Bowen says it won’t be cancelled

Published by

The head of Snowy Hydro has apologised for large cost blowouts but has promised Australia’s largest renewable energy project will still show a return on investment for taxpayers.

The company revealed the cost of the troubled project had increased to $12 billion, six times more than what was originally budgeted.

When the project was announced in 2017 by former prime minister Malcolm Turnbull, it was expected to be finished in 2021, but now it’s not set to be finished until December 2028.

Snowy Hydro chief executive Dennis Barnes, who was appointed to the role in February, said he was confident the cost would not blow out further.

“Obviously (we’re) very disappointed in the cost increase, and of course we apologise for that, but bear in mind that this is an investment that the Australian taxpayer will get a return on,” he told ABC Radio on Friday.

“I’m very confident $12 billion (and) 2028 is a good target for us to achieve.”

The company said as of June $4.3 billion had been spent on the project, while 80 per cent had been reinvested into the economy.

It’s expected the first power from Snowy 2.0 would be delivered in the second half of 2027, while the whole project would be operational by the end of 2028.

Barnes said increased construction costs and flow-on effects from COVID-19 contributed to the cost blowout.

“We’ve done an awful lot of work, which is really rigorous work … we’ve learned a lot in the 40 per cent of the project we have completed, so it gives me a degree of confidence,” he said.

While there were “no guarantees”, he was comfortable with the trajectory of the incredibly complex project.

The energy project had been hampered by softer than expected ground, which had held up the tunnel boring machine.

Barnes said the project was waiting for approvals from the NSW government for modifications to the Snowy 2.0 plan to be able to continue tunnelling efforts.

So far, the machine had only moved 180 metres out of the planned 17km tunnel.

“We’ve been getting ready to move through this soft ground. We obviously take our environmental obligations incredibly seriously,” he said.

“We want to make sure that when we do move forward, we don’t encounter any problems.”

Energy Minister Chris Bowen said financial incentives had been offered for contractors who deliver services on time and on budget, while penalties would apply if targets were not met.

He told radio today: “The analysis shows that there’s still $3 billion net value, and of course is 40 per cent built, so it would be a huge waste of money to cancel it at this point.”

See also this analysis: Snowy 2 Much: How can a 2.2GW water battery be worth more than $12 billion?

AAP

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024