Policy & Planning

Snowy confirms controversial and costly NSW gas plant will start operations fuelled by diesel

Published by

Snowy Hydro has confirmed that its new “fast-start, on demand” hybrid hydrogen and gas plant being developed in the New South Wales Hunter region will start its operational life running on costly and polluting diesel fuel.

Snowy Hydro’s controversial 660MW Kurri Kurri Hunter Power Project, which got its start under the Morrison Coalition government, was kept alive by federal Labor, with the promise of $700 million more in public funding on the condition it was built “hydrogen ready.”

It was soon revealed, however, that the plant will start out using fossil gas only, and that moving to just 15 per cent green hydrogen will be subject to construction delays and lack of availability of the zero emissions fuel.

The project has also come under fire for its costly gas supply and storage challenges, due to its location beyond the end of the Sydney-Newcastle gas trunkline, requiring a 21 kilometre lateral pipeline connection as well as an on-site storage pipeline. 

By the end of 2023, the project’s cost had blown out from $600 million to $930 million – although, according to some estimates, it is likely to soar past $1.5 billion when the full costs of the gas pipeline connection and gas storage are factored in.

It has also become clear that diesel will be a major part of the power plant’s early generation equation – quite a long way from green hydrogen – until gas supply and storage infrastructure can catch up with the rest of the development.

In an update published on Wednesday, the federal government-owned gen-tailer said the Hunter Power Project (HPP), was on track to come online in December, with the start of testing and commissioning phase of one of its two generators on diesel fuel.

“When operating on diesel each unit is capable of generating 283MW,” the project update says. “This is the quickest path to ensuring HPP is available to provide power to the electricity network, which will occur as soon as possible after testing is complete.

“We will sequence the commissioning of the second unit and the introduction of gas. We expect HPP to be fully operational, with both generators able to operate on both fuels, in the few months following the start of testing.

“Snowy Hydro’s investment in the Hunter Power Project (HPP) will play an important role as coal plants close,” the statement continues. 

“With 660 MW of available dispatchable capacity, supported by 34 hours of onsite fuel storage from 70 terajoules (TJ) of gas and 3.6 million litres of diesel, HPP will be capable of enabling approximately 2 gigawatts (GW) of new renewable capacity.”

Critics of the project, however, are not convinced that the Hunter plant will be all that useful to the rapidly changing Australian grid – and whether its huge costs, both financial and environmental, can be justified.

“HPP’s storage will be massive, Australia’s largest, consisting of 24 kilometres of one-metre diameter pipe in a labyrinth arrangement, storing 70 terajoules at high pressure,” energy expert Ted Woodley wrote here last year.

.”Even so, it will only be sufficient to power the turbines for 10 hours at full output. It will then take more than a day to refill, provided of course there is gas available to purchase from the heavily committed trunkline.

“Hence, HPP is incapable of providing dispatchable energy 24/7,” Woodley argues.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

NSW to invest $60 million to local communities, years before first poles erected in new renewable zone

NSW fast-tracks $60 million in community funds to help head off community concerns about the…

14 May 2026

Australia’s growing throng of solar panels, home batteries and electric cars to be managed by new regulator

Australia's growing throng of solar panels, batteries and electric cars will be managed by a…

14 May 2026

A “keep out” sign for investment: Alarm bell sounds over new retrospective tax on renewables

Industry says retrospective tax on renewables announced in budget could deter foreign investment when it's…

14 May 2026

Diesel backup gensets are big winners from the data centre boom. Our cities would be better off with batteries

One of the segments flowing rivers of gold from the data centre boom is backup…

14 May 2026

Bizarre planning rules that force new home owners to pay for gas connections, whether they want it or not

The bizarre planning rules that make fossil gas connections a default for new homes, and…

14 May 2026

Energy Insiders Podcast: Budget’s fossil fail, and how to fix the CIS

Tim Buckley from Climate and Energy Finance joins to discuss the good, bad and the…

14 May 2026