NSW Government

Snowy 2.0 seeks approval as landfill proposal labelled “environmental vandalism”

Published by

The NSW Department of Planning, Industry and Environment (DPIE) has issued a call for feedback on the Environmental Impact Statement (EIS) for the “main works” to be undertaken as part of the Snowy 2.0 pumped hydro project, which is attracting fierce criticism for its potential impacts on the Kosciusko National Park.

At the core of the Snowy Hydro 2.0 expansion will be the establishment of a new underground tunnel linking the Tantangara and Talbingo reservoirs and the commissioning of a new underground power station that will operate as Australia’s largest pumped hydro energy storage system.

The main works for the Snowy 2.0 project will include the removal of an estimated 9 million cubic meters of excavated rock. The federal government owned Snowy Hydro has proposed that more than half of this excavated material be relocated within either the Talbingo or Tantangara reservoirs, with the remaining material used to establish permanent structures, or for land forming.

The Snowy 2.0 project, the pet project of former Prime Minister Malcolm Turnbull, and embraced with enthusiasm by current energy minister Angus taylor (whose grandfather was chief engineer on the original scheme) will substantially increase the amount of water storage within the Snowy Hydro scheme.

This will include the addition of 2,000MW of pumped hydro energy storage capacity, and 175 hours of storage, or a total of 350,000MWh of energy storage.

“If approved, the Snowy 2.0 Main Works would involve the construction of an underground power station with a generating capacity of around 2,000 megawatts and approximately 27km of power waterways linking the existing Tantangara and Talbingo Reservoirs,” the DPIE executive director of resource assessment David Kitto said.

“It could increase the generation capacity of the existing Snowy Scheme by almost 50 per cent and provide 350,000 megawatt-hours of large-scale storage capacity for the National Energy Market.”

“We appreciate the level of community interest in this project, and we want to give the community sufficient time to have their say. This is why we are exhibiting the EIS for the project for six weeks, which is two weeks longer than the normal exhibition period,” Kitto added.

The project is already facing calls from environmental groups to be scrapped, with the National Parks Association of NSW saying the project represents an unacceptable impact on the biodiversity and environmental value of its surrounding national park.

“Snowy 2.0 should not even be contemplated in the first place, due to its substantial, permanent damage to Kosciuszko National Park,” NPA executive officer Gary Dunnett said.

“Snowy 2.0 has been portrayed as a silver bullet for resolving the future electricity market and the transfer to renewable energy.”

“But, not only is Snowy 2.0 environmental vandalism, it isn’t economic. The original $2 billion cost estimate is now approaching $10 billion (including transmission).”

The Federal government owns Snowy Hydro Limited, after it purchased the shares previously owned by the NSW and Victorian governments for a combined $6.1 billion in 2018.

The Snowy 2.0 expansion is expected to cost an additional $5.1 billion, with an additional $2 billion in investment required to boost the network infrastructure connecting the Snowy Mountain scheme with the rest of the National Electricity Market and will take more than six years to complete even with a workforce working around the clock.

“Construction of Snowy 2.0 will be 24/7 and 365 days per year. The construction workforce is expected to peak at around 2,000 personnel in 2023 but will fluctuate over the six-year construction schedule as needed to align with the work activities,” Snowy Hydro Limited says in the EIS.

Snowy Hydro 2.0 will represent one of the largest single infrastructure projects underway in Australia, and will substantially reshape the operation of the National Electricity Market, with the addition of such a large amount of dispatchable energy storage.

Snowy Hydro estimates the project will increase the Gross State Product of NSW by $2.692 billion and will have additional flow-on benefits to the other NEM participant states of $4.176 billion-

The EIS is seeking input from interested parties on the potential impacts of the project on the environment, including the impact of new tunnels, modifications at the Tantangara and Talbingo reservoirs, and the underground power station and network infrastructure.

Submissions responding to the proposed environmental impact statement are open until 6 November.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by
Tags: Snowy Hydro

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024