Snowy 2.0 contractor drama continues, with talk of sale raising new concerns

Published by

Snowy 2.0 contractor Clough Engineering is reported to be up for sale in a development that could hold implications for the delivery of the massive federal government-backed pumped hydro project in New South Wales.

South Africa-based Murray & Roberts, which owns Clough – a 35 per cent partner in the consortium building Snowy 2.0 – revealed in September that Clough had no working capital facility, describing the situation at the time as “ludicrous,” RenewEconomy has reported.

The decision by Clough and Murray & Roberts to pursue a sale may have been forced partly by mounting financial difficulties, with a string of problems at big projects piling pressure on its balance sheet, reports said on Monday.

(See latest update: Snowy contractor shares plunge after it reveals “acute” working capital issues

Webuild of Italy, Clough’s joint venture partner on Snowy 2.0, is the only company remaining in early negotiations to buy the Western Australia-based contractor, according to unidentified sources cites by The Australian.

Clough did not immediately respond to a request by RenewEconomy for comment.

Webuild, previously known as Salini Impregilo, already holds a 65 per cent sake in the joint venture, having won a $5.1 billion fixed price contract from Snowy Hydro in 2018. A purchase of Clough would give Webuild 100 per cent of the contracting work and greater control over the timeline of the project.

Reports of the potential sale of Clough only heighten concerns over the progress of Snowy 2.0, already the subject of heated debate over its market benefits and its economic impact.

Over time and over budget

Earlier this year, reports emerged that the project is running more than $2 billion over its already inflated budget of $5.1 billion (not including transmission). Rumoured delays to the project’s delivery of up to 18 months have not been communicated to the market operator.

Webuild Asia-Pacific director, Marco Assorati told the Australian Financial Review in July that delays on Snowy 2.0 were not due to geotechnical challenges but instead to the difficulty of bringing in fly-in, fly-out workers to a remote location during the pandemic, and the project’s technical complexity, which requires people with specialised skills,

In August, Snowy Hydro’s chief executive, Paul Broad, suddenly resigned after years at the helm of the government-owned utility, with some reports saying he was “sacked.”

Snowy 2.0 is not the only energy project in Australia that could be altered if Clough is sold and delays stretch out.

The company is also building for Transgrid the NSW part of the $1.5 billion Project EnergyConnect transmission link between South Australia and NSW, currently up to a year behind schedule.

Share
Published by

Recent Posts

Australia wants to add 1.8 billion tonnes of thermal coal in face of declining market conditions

Australia’s thermal coal pipeline seems dangerously misaligned with market and climate realities in a landscape…

15 December 2025

Two new big batteries energised on grid, underlining speed and scale of storage rollout

Two new big battery projects have been energised on Australia's main grid in the past…

15 December 2025

State launches rooftop solar for renters rebate into renewables policy vacuum

Days after dumping its renewable energy targets and pledging billions of dollars in support of…

15 December 2025

From Rhombus of Regret to on-time commissioning: Australia’s biggest wind farm finds blueprint for grid success

Australia's biggest wind farm has been commissioned on time, and may have found a blueprint…

15 December 2025

Flexible payments versus sun tax: Groundbreaking rooftop PV exports trial to continue through 2026

A groundbreaking trial to test an innovative alternative to rooftop solar export tariffs will run…

15 December 2025

Wanted, more batteries as abundant wind and solar hit record curtailment levels

Abundance defines the day as wind and solar curtailment hits new peaks, accounting for more…

15 December 2025