A small but long delayed Tasmanian wind project has finally begun construction in the north west of the state, after benefitting from a planning extension and being the subject of debate in state parliament.

The Singapore-based Aquila Clean Energy Asia Pacific has started construction on the 21 megawatt (MW) wind farm in Port Latta, just east of Tasmania’s windy hotspot Woolnorth. 

The wind farm was granted planning approval in 2019, and had a federal environmental nod that it wouldn’t need EPBC approval in 2018. 

But by the end of the last year, it was bumping up against the end of its five year development permit because it couldn’t get an offtake deal with Hydro Tasmania, according to a debate in the state’s parliament in June last year. 

The Port Latta wind farm will consist of five 4.5MW turbines spread across two private properties, and will connect to TasNetworks’ local sub-station.

It’s expected to be ready for commissioning later this year.

Why so long?

It’s unclear why the Port Latta project has taken so long to start construction, but two parliamentary debates in the last 12 months hint at why. 

In June, an opposition MP revealed that Aquila hadn’t started building the project, despite having approvals in place, because of a lack of offtake agreement with the state hydro company. 

“Will you direct Hydro to enter into such an agreement and finally get this project started?” asked opposition MP Janie Finlay. 

Energy minister Nick Duigan’s response was that he wouldn’t interfere in commercial decisions at Hydro Tasmania. 

However, the government later put up an amendment to planning laws, which was passed in December, allowing ministers to give extensions to complicated projects, and specifically naming Port Latta in the ensuing debate. 

Independent MP Ruth Forrest suggested the delay was due to supply chain issues but admitted she didn’t know exactly why the company had left things so late. 

Aquila has been contacted for comment. 

Forrest also said the Port Latta project was one of the projects that triggered the amendment.

It allows ministers to supersede councils and give two-year extensions to local development approvals for projects that are “technical or complex” in nature – language that Forrest believed was fine for uncontroversial and broadly supported Port Latta but which could cause problems in future for other developments that don’t have community or council support. 

A grateful LinkedIn post by Aquila over the amendment in late November claimed the project was “complex and technical” in nature. 

“This amendment enables the Planning Minister to grant projects in Tasmania an extension of the DA and therefore provides… the extra time needed to move from its ready-to-build stage through to the commencement of substantial works,” it said.

It’s not clear what about the project is technical, given it has local support, council approval and according to its December newsletter update does not require a new transmission line or an onsite substation to connect to the local grid.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Licences sought for Australia’s biggest wind, solar and battery hybrid to power giant gold mine

Licences sought for what will be the biggest wind, solar and battery hybrid of its…

11 August 2026

Pakistan’s citizen-led solar rush: Where panels power education and health – and are gifted in dowries

In Pakistan, a country with 250 million people and a GDP per capita of about…

11 August 2026

Plans for one of Australia’s biggest new gas plants sail through EPBC queue in just over two weeks

As wind generation proposals get stuck in EPBC limbo, plans for what could be the…

11 August 2026

Last turbine goes up as major wind farm completes expansion to become biggest in state

The last of 30 additional turbines have been added to existing wind farm, making it…

11 August 2026

Investor behind Amber Electric hits $10 million under management, milestone for new fund

Sydney based early-stage climate technology investor reaches $10 million under management and secures first close…

11 August 2026

SwitchedOn podcast: Biggest barrier to electrifying apartments? Knowing what’s possible

Strata manager Ash Sayers explains why getting the right advice early can turn apartment electrification…

11 August 2026