“Significant milestone:” Off-grid mine runs 155 consecutive hours on 100 pct renewables and engines off

Published by

The Bellevue gold mine in a remote part of Western Australia is claiming another major record after completing 155 consecutive hours running the facility on 100 per cent renewables, and with “engines off.”

The gold mine – with an average load of around 12.5 megawatts (MW) – – has achieved average renewable shares of well above the 80 per cent it targeted, often reaching into the 90 pct range on a monthly basis, and an average 93.8 per cent over February.

In early May, the facility ran for more than six and a half days running entirely on renewables – courtesy of its 27 MW of solar, 24 MW of wind, and the 15 MW, 33 MWh of battery that stores excess output and sends it back to the micro-grid when needed.

“This is a significant milestone, not only for the project, but for what is possible in the Australian energy sector and demonstrating nation-leading progress in renewable energy for remote mining operations,” Zenith Energy, which built the hybrid power station, wrote in a LinkedIn post.
 
“The system is designed to meet at least 80% of site energy needs from renewables, and moments like this show what that looks like in practice – especially with the right weather conditions.”

Bellevue Gold already claims to be the world’s first net zero emissions gold mine (scope 1 and scope 2), although it achieves some of this with offsets, and is yet to decarbonise its mining equipment and transport, as Fortescue is aiming to do by 2030 at its much bigger iron ore operations in the Pilbara, where the average load is 800 MW.

Still, the new record for “engines off” is believed to be a world first at such a facility relying on wind and solar as the major source of power, and beats the achievements of the much smaller King Island mini-grid off the coast of Tasmania, where the average load is around 2.5 MW.

A number of different off-grid mines are achieving very high level of renewables – usually much higher than predicted – with Lynas Gold achieving a record 95.7 per cent renewable share over the entire March quarter at its Mt Weld lithium mine.

Another lithium miner, the Kathleen Valley facility operated by Liontown Resources, has also achieved high share of renewables above 80 per cent on a consistent monthly basis, shielding it from the recent surge in diesel prices.

Both Lynas Gold and Liontown are backed by Gina Rinehart, Australia’s richest person, and one of its most ardent anti-renewable campaigners.

Bellevue said in April that it is on track to meet the upper end of the forecasted 80-90 per cent renewable energy for the current financial year.

“As well as reducing emissions, the high fraction of renewable energy has inherently decreased Bellevue Gold’s exposure to fluctuations in the diesel and LNG markets, and provides extra resilience to any potential supply chain shocks,” it said in its quarterly statement.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.
 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s Atmos snaps up wind and solar projects as European developer retreats to core markets

Australian developer snaps up portfolio of operating and developing wind and solar projects as a…

17 October 2026

A massive 244-tonne transformer completes 2,165 km road trip to Australia’s largest solar project

A massive 244-tonne transformer has completed a 2,165 km road trip to the site of…

17 October 2026

Energy Insiders: Grid scale sodium batteries are on their way

The battery industry is about to witness another change in chemistry and technology. Valo Energy…

16 October 2026

“Just a fantasy:” Energy minister slams Opposition gas and nuclear ideas, vows to hold the line on renewables

Energy minister says imminent closure of coal is "indisputable," and "ideology-driven" policies to scrap transmission…

16 October 2026

Supplier to Australia’s biggest battery expects to announce first sodium-ion battery project soon

The supplier to the biggest battery currently being built in Australia expects to announce its…

16 October 2026

Wind projects will need help “for a while”, says new green bank boss in shift of funding priorities

The federal government green bank has dusted off an old mandate, but has not ruled…

16 October 2026