SA Water set to add another 5MW solar, including floating PV array

Published by

One Step Off The Grid

South Australia’s largest water and sewerage services supplier, SA Water, is set to install another 5MW of solar PV, including a floating solar plant, after local outfit Enerven was awarded the tender for the job.

Enerven said on Wednesday that it had won a Stage 1 contract to design and construct ground-based solar installations at facilities in Hope Valley, Christies Beach and Glenelg, and to develop a floating solar PV array.

SA Water, which has targeted zero net energy by 2020, began its shift to solar last year, with a tender to install 100kW solar and 50kWh battery storage at its Crystal Brook Workshop site.

The utility, which manages more than 27,000km of water mains, including 9,266 km in the Adelaide metropolitan area, said it was installing the solar and storage system to manage periods of high electricity prices, and to ensure safe and sustainable delivery of water to customers.

Ultimately, the company aims to get its on-site renewable energy generation to the point where it is equal to the total annual amount of energy used by SA Water’s buildings and desalination operations.

And it is not alone in its quest. As we have reported on One Step Off The Grid, a number of Australian water utilities are turning to solar and/or wind energy to lower costs and help guarantee supply.

In Queensland, Logan City Council has installed an off-grid solar and battery storage system as part of a micro-grid powered “electro-chlorinator” that will help maintain local drinking water quality 24 hours a day.

The solution – delivered by the Logan Water Infrastructure Alliance and solar installer CSR Bradford – combined a 95kWh Tesla Powerpack with 323 PV panels at the site of the relatively new 20 Megalitre Round Mountain Reservoir, which provides drinking water for residents in Flagstone, Yarrabilba, North Maclean, Spring Mountain and Woodhill.

In the regional Victorian city of Portland, Wannon Water has installed a 100kW solar system on a water tank at its treatment plant at Hamilton that was expected to cut the plant’s grid electricity consumption by 25 per cent.

In NSW, a community-funded 100kW floating solar array has been installed at the East Lismore Sewage Treatment Plant in NSW.

And Queensland’s City of Gold Coast is proposing to install a series of floating solar PV arrays on its network of wastewater ponds – both to help power the city’s wastewater treatment plants and to cut evaporation from the ponds.

Enerven says design of the SA Water solar project has commenced, and is due for completion in September 2018.

This article was originally published on RenewEconomy’s sister site, One Step Off The Grid, which focuses on customer experience with distributed generation. To sign up to One Step’s free weekly newsletter, please click here.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Hunter Valley collieries to be greened-up as clean industrial hubs in “post mining land transformation”

State and federal governments aim for 7,000 green and industrial jobs under new master plans…

14 July 2026

“We cannot wait:” Changes made to renewable tenders to ensure wind and solar projects actually get built

Key changes have been made to renewable tenders to ensure that the winning projects can…

14 July 2026

Coal closure delays and soaring prices mean more batteries and fewer syncons to keep heartbeat of grid

Soaring syncon costs and supply issues, along with delays to coal closures, is opening up…

14 July 2026

Spitting chips: A deep dive into the data and token industry, and who carries the GPU risk

This note provides an estimate of demand and supply of tokens, draws a conclusion about…

14 July 2026

Wind project with an 8-hour battery hybrid looks for final green light after speeding through state approvals

A new wind-battery hybrid project speeded through state approvals, now it needs one more nod,…

14 July 2026

Graph of the Day: Half-time and hydration breaks lift grid demand in England and Norway World Cup game

England and Norway experienced big surges in demand during half time and hydration breaks in…

14 July 2026