S.A. network operator to trial micro grids for regional towns

Published by

The operator of the South Australia electricity network says it is to trial micro-grids with solar and battery storage in regional areas as a potentially cost-effective alternative to building or replacing poles and wires.

SA Power Networks, in its latest submission to the Australian Energy Regulator for spending over the next five years, says “micro-grid” technology has “particular promise” – both as a cheaper alternative to diesel, and as a potential solution to weather related black-outs that frequently plague regional areas.

In its submission, SA Power Networks says it needs to upgrade 31 remote power lines, and it will use a solar and battery storage based micro grid for one one them – at a cost of $2.8 million.

It will be a combination of distributed storage and centralised storage, and will be considered as a future alternative option to remediate reliability or defer augmentation to remote communities.

Although micro-grids have existed for many years, both for individual customers and communities, they have generally relied on diesel generation as their prime means of electrical supply when islanded,” the company said in its submission.

“These types of systems are prohibitively expensive other than for customers that place a very high value on reliability of supply (for example, hospitals and data centres) or for customers that are remote and for which a grid connection is uneconomic.

“With the continued advancement of solar PV distributed generation capabilities, and anticipated cost reductions in battery storage technologies, new opportunities are arising for more cost effective micro-grids.

“With significant local generation already in place (solar PV) and if a material number of customers also take up battery technology, this investment by individual customers may be able to be leveraged to maintain supply to an entire community should that community’s network connection fail.”

SA Power Networks predicted last year that regional communities would ultimately focus on micro-grids, which would rely on renewables and storage, and could either be “stand-alone” or connected to the main grid with a “thin wire” as back-up. The savings to the network operator could be significant.

In Queensland, Egon Energy is now installing battery storage as a cheaper and more reliable alternative than upgrading the wires that connect coal fired power stations to regional consumers, and Western Australia is also looking to micro-grids as an alternative to “costly and unreliable” centralised grids.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Northern Hemisphere extreme heat records just a warm up for the full El Niño theatre

We've seen impacts of the record-breaking El Niño in the Northern Hemisphere – including heat-related…

12 August 2026

The NSW koalas-for-coal shakedown – and what it reveals about the carbon offset market

The NSW government's plan for a Great Koala National Park now includes seeking the rights…

12 August 2026

NSW won’t rule out slippages to coal closure timetable, as first turbine deliveries highlight lack of new projects

NSW energy minister says government will make "hard decisions to extend" coal closures where required,…

12 August 2026

Why solar didn’t work for this dairy farmer, until he added a battery and put it on wheels

High hot water use, an unreliable grid, and milking in the dark were all challenges…

12 August 2026

Coal will close to schedule, says AGL, but to build more wind we need policy certainty in return

AGL says it will stick to its dates for coal plant closure, but wants policy…

12 August 2026

“No silver bullet:” Wind farms need site-specific technology to avoid bird and bat turbine collisions

No one system prevents bird and bat turbine collisions, but a mix of strategies from…

12 August 2026