Robots are coming! Machines being tested at solar projects for pile driving as well as mounting panels

Published by

Neoen is not the only renewables developer testing out a robot: the contractor at Engie’s Goorambat East solar farm is also trialling autonomous machines, this time for pile driving.

The Build Robotics device started in February and finished installing 1700 piles in mid-April. It secured $1`.3 million in funding from the Australian Renewable Energy Agency (ARENA) in November to fine-tune the system.

The prototype is still significantly slower than using humans, but also much, much quieter than the traditional method of punching piles into the ground, says Bouygues Construction Australia project director Bastien Sauvet.

“You have two machines, both are autonomous. One putting the piles in position and the other one installs and vibrates to put it in a good position,” he told Renew Economy. 

“They are not quicker than a team of humans because they did 120 piles per day when on average [with the traditional method] we can do over 250.”

The machines use AI, GPS, and sensor technology to precisely drive piles with minimal human oversight by Sauvet and Equans Solar and Storage which is also running the trial. If a human goes inside a specified perimeter, they automatically shut off to prevent accidents.

A new technique of vibrating piles into the ground rather than hammering reduces noise levels by 20 per cent, Sauvet says. 

That’s a detail that will go a long way towards being a good neighbour and to protect nearby workers’ hearing. 

Scale ups and desert work

With jobs on the line, the use case for autonomous machines that Suavet, along with Engie’s local representative, Neoen and other renewables developers say they are considering is on bigger projects in areas too harsh for human workers.

The Gurambat East solar farm in Victoria is 250 megawatt (MW), mini when compared to wind farms being proposed today, while Neoen’s Culcairn project in New South Wales is 440 MWp / 350 MW (ac), its second largest solar farm worldwide.

Engie is seeking to build projects that are significantly bigger — as large as 800MW.

But with humans currently needed to lift modules into place (up to four, according to Neoen’s robot supplier, Leapting), to install piles and generally have a hand on each part of the process, the labour needs to build solar projects at that scale while meeting labour regulations will be significant.

Or as one industry source told Renew Economy, for an 800 MW solar project do developers choose to bring in twice the number of people, make the build time twice as long, or just use robots?

A question solar developers are grappling with is that in desert areas, such as Sun Cable is planning with its 20GW of solar south of Darwin and Engie is hoping for with a bid in for an auction of 3GW of solar in Saudi Arabia, is whether those areas are safe for people to work for long periods outdoors.

“We have more projects in desert areas where it’s difficult to get manpower, where the land is huge and the solar farms are bigger and bigger,” Suavet says.

One project, built in the Pilbara, delivered a withering assessment of conditions in remote arid regions. See our story: Hot, humid, dusty and …. boring: Building solar farms in the outback is not piles of fun

The jobs question

The elephant in the room, however, is of course the number of jobs that will be lost to autonomous machines.

The number of jobs created by renewables project construction and ongoing operations and maintenance are now included near the top of both development applications and in government announcements.

That alone suggests any moves to improve efficiency via robots in highly populated regions might run into pushback from communities and from governments trying to sell the renewable energy dream.

Although it should also be pointed out that some of the pushback from local councils is over the question of where and how to accommodate the temporary workforce.

Engie’s Leigh Newbery expects that ultimately a robot like the Build Robotics pile driver will reduce the time it takes to the job and allow work to continue for longer in the day because of the lower noise levels. 

“It requires skilled technicians to operate it, thus upskilling the current renewable energy workforce and enabling more productivity,” he said in a statement.

“The intended higher productivity will reduce the cost of renewable energy projects and enable projects to be built in less time – which will bring down energy costs for consumers and potentially allow more renewables to be built.” 

When Build Robotics won the ARENA grant last year, the company was firm that people will still be involved in its system but will need bigger skills sets.

The piles still need to be organised onto the machines and configured, then everything taken to the site, the company’s communications lead Lauren Lee told Energy Source & Distribution last year.

Those “robotic equipment operators” are currently Built Robotics trained or the company’s own employees. Lee said they want to create a workforce of people who can operate robotic equipment.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by
Tags: Engie

Recent Posts

Australian households installed record amount of rooftop solar and home batteries in first half of 2026

Australian households have installed a record number of rooftop solar systems and home batteries so…

29 September 2026

Trump unable to stop clean energy revolution, as wind and solar output surges and coal shrinks

Trump administration appears to have bet on the wrong horse, with renewables surging and coal…

28 September 2026

Home battery owners need more flexibility to break resistance to VPPs, Rewiring Australia survey finds

Few home battery owners have signed up to join virtual power plants, with concerns about…

28 September 2026

The off-grid mines leading the charge towards 100 pct renewables | Energy Insiders

Zenith Energy’s Michael Buzzard on the remarkable energy transitions achieved in off-grid mines, and plans…

28 September 2026

“Too much wind and solar?” The state-wide blackout and the dinner party that changed the course of history

It is 10 years since South Australia's state-wide blackout: Far from being the end of…

28 September 2026

Social housing tenants to get coordinated rooftop PV and home batteries in first urban renewable zone

First urban renewable energy zone to host pilot program to demonstrate how social housing tenants…

28 September 2026