Risen Energy’s Yarranlea Solar Farm construction completed and compliance testing phase underway

Published by

PRESS RELEASE

Construction of Risen Energy (Australia)’s 100 megawatts AC Yarranlea Solar Farm was completed in August and the facility has entered the commission and compliance phase.  This will continue for several months and include compliance testing with the Australian Energy Marketing Organisation.

“We are currently in the continuous testing phase which is dependent on the network service provider and network operators and will be commercially operational in early 2020” said Eric Lee, General Manager Risen Energy (Australia).

“Part of the commissioning is considering network constraints and we are working with Ergon Energy to maximise power output while minimising impacts to the network”, said Lee.

The solar farm and associated substation infrastructure have been successfully energised using the local distribution network to allow compliance and functional tests to be undertaken. The Australian made 33/110kV transformer that will connect the solar farm to the transmission network, is also in the final stages of commissioning by Wilson Transformer Company.

The Yarranlea Solar Farm is located near Pittsworth, about 50km west of Toowoomba on the Darling Downs. The solar farm is approximately 250ha in area and consists of over 360,000 Risen solar panels mounted on a single axis tracking system.  The farm will generate and deliver clean, renewable electricity to power up to 32,000 homes.

The Yarranlea Solar Farm is connected to the power grid using the existing Ergon Energy infrastructure, located close to the farm site. This allows transmission of power into the Middle Ridge Bulk Supply Substation, ultimately supplying green power to homes, businesses and industries in the Toowoomba and Darling Downs area.

The completed facility has a projected life of 30 years. At the end of the facility’s useful operating life, all physical infrastructure will be removed, and the land returned to its former agricultural use.

The Yarranlea Solar Farm will contribute to the green footprint of the state in support of the Queensland Government’s Green Policy.  Risen Energy (Australia) as the owner of the Yarranlea Solar farm has worked within the Queensland Government’s Solar Farm Guidelines which provide a practical guidance for communities, landowners and project proponents.

“Risen Energy (Australia) has progressed the project from detailed engineering design, through construction, commissioning and ultimately the operation of the solar farm.  We used our latest PV panel technology to supply power to the grid. Ultimately, integrated battery storage will be incorporated in the solar farm to provide continuous power during periods of peak demand” said Lee.

Share
Published by

Recent Posts

Energy Insiders Podcast: “I don’t know if we can adapt”

WMO’s climate and energy lead Roberta Boscolo on the latest climate report, the 1.55°C average…

31 January 2025

Queensland unveils strict new wind farm planning rules, with solar projects to follow

LNP introduces strict new planning rules for wind projects in state with lowest share of…

31 January 2025

Neighbours of giant wind project offered up to $100m in unique deal that could shape design

Near neighbours of one of the country's biggest wind projects are being given the opportunity…

31 January 2025

Farmers offered $300m in discount loans for solar, batteries, EVs, seaweed and windbreaks

Farmers offered up to $300 million of discount loans to help efforts to cut emissions,…

31 January 2025

Biggest vanadium flow battery in Australia promised for ailing Kalgoorlie grid

A 500 MWh vanadium flow battery - the biggest in Australia - has been promised…

30 January 2025

Big batteries cash in as they charge past gas to become second biggest player in evening peaks

Big batteries have overtaken gas as the second biggest player in the evening demand peaks,…

30 January 2025