Battery

Risen Energy to build its first big battery in Australia with “gamechanger” Arena funding

Published by

Risen Energy will build its first big battery in Australia, after its 200MW/400MWh Bungama project was one of eight tapped to receive funding from the Australian Renewable Energy Agency over the weekend.

The Bungama battery energy storage system project (BESS) in South Australia will be located adjacent to the 275/132 kV Bungama Substation near Port Pirie in South Australia.

The battery project, which is already approved for development and is currently awaiting grid connection approval, will feature grid forming inverter technology – a focus of Arena’s funding round for large-scale energy storage.

Risen CEO Archie Chen says the “gamechanger” funding from Arena has enabled the company to incorporate advanced inverter functionality in the battery’s design, when it otherwise might not have been considered.

“The funding will also enable us to provide the best possible solution for the project and the learnings attained from Bungama will benefit similar BESS projects in our pipeline,” Chen says.

The inverter technology Chen refers to means that big batteries can provide most, if not all, of the crucial grid services currently provided by coal plants, which in Australia are expected to close over the coming decade.

This is a particularly important service for South Australia, which is forging ahead on the path to 100 per cent “net renewables,” and which over the last week saw renewables average at 104.1 per cent of state demand.

Risen says the Bungama BESS will play an important role in strengthening the South Australian energy network and will likely become the home for several other large generator and/or load connections.

Notably, another completely separate solar and big battery project is being developed in Bungama by Toronto-based Amp Energy, in this case with 336MW PV and a 150MWh BESS.

For Risen, while the Bungama battery will be the China-based company’s first in Australia – the project is expected to be operational by mid to end 2024 – it has more of the same in its project pipeline.

A spokesperson tells RenewEconomy Risen Energy Australia has three other BESS projects and one solar and BESS hybrid project along various stages of the developmental pipeline.

The company has also developed two solar projects in Australia, including the Yarranlea solar farm in Queensland and the Merredin solar farm in Western Australia, which it sold to Sun Energy.

See RenewEconomy’s Big Battery Storage Map of Australia

TagEnergy to press go on big renewables hub in north Queensland after battery win

“Like riding a bike:” First big battery in Australia;’s biggest coal grid enters full production

 Neoen to add big battery to what is now Australia’s biggest solar farm

 

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Institutions

Recent Posts

Australia can still become a giga-scale solar manufacturer, says Arena, as it flags new local PV maker

Australian Renewable Energy Agency says the country can still become a major solar PV manufacturer,…

16 October 2026

Approval sought for another huge wind and battery hybrid as state prepares to move beyond coal

Plans for a massive wind farm with 92 turbines and an up to eight-hour battery…

16 October 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

Search begins for new ARENA CEO, changes at the SEC, new CEOs for Momentum, CS…

16 October 2026

Spanish giant wins contracts for transmission projects to connect offshore and onshore renewables

Spanish energy giant snags two major transmission contracts at opposite ends of Australia – one…

15 October 2026

Wind developer signs community benefit deals worth up to $160m to end stalemate over called-in projects

UK developer and local council sign community benefit deals for two projects stuck in limbo…

15 October 2026

Grid-scale renewables hit record levels of investment sign-offs, but the pace still needs to quicken

A record amount of large-scale renewable generation has reached financial close, the federal government says,…

15 October 2026