Restoring the grid after a blackout — using batteries

Published by

CleanTechnica

In a German premiere, a grid-scale battery storage system is to provide “black start capability” – the ability to restore a regional distribution grid in the case of major disruption to the network – a service provided until now only by conventional power plants.

Berlin-based energy storage and grid solutions provider Younicos announced last week that Europe’s first commercial battery park, a 5MW/5MWh system operated by the local utility WEMAG, will be upgraded to become the first battery storage system in the country capable of restoring the local grid in conjunction with renewable energy sources and a gas and steam power plant.

Some background: If an electricity transmission system suffers a partial or total shutdown, the inevitable loss of supply makes restoring the grid to normal service a big challenge. Large conventional power stations usually need a helping hand to restart in the form of power from the grid.

If the grid cannot supply the necessary power, then an onsite auxiliary generator is used for a so-called black start. Power stations are then restarted one by one and progressively reconnected to the grid.

While power plants aren’t always required to have black start capability, operators are usually paid to keep the service available and can receive a fee should a black start be necessary. While the chances of even a partial shutdown are remote, the ability to restore power to the grid is essential.

The Schwerin-based battery park will now offer this service in addition to the frequency regulation it has provided until now. Younicos will “extend the battery system’s functionality to make it capable of black starts, full islanding mode and integrating renewables in grid restoration scenarios” as part of the “kickstarter” demonstration project, the company stated in a press release.

Thomas Pätzold, Chief Technical Officer at WEMAG, said: “Our project once more demonstrates the wide range of use cases and income streams that intelligent battery systems can provide. The battery has already generated higher revenues than expected in the primary control market, and we’re sure that this upgrade will be another worthwhile investment.”

The project is being supported with funding from the “Viable Future Electricity Grids” initiative of the German Federal Ministry for Economic Affairs and Energy and will run for three years.

Source: CleanTechnica. Reproduced with permission.

Share
Published by

Recent Posts

Data centres to get faster nod if they meet energy, grid and water needs

State says data centres will "need to pay their own way," including bringing additional electricity…

17 August 2026

No, Ray Hadley, the collapse of Zen does not mean renewables have failed, nor that more coal will be burned

Zen Energy's failure has inspired the usual suspects to claim renewables don't work. Curiously, planes…

17 August 2026

“It’s literally life-changing for us:” The drought-stricken farmers looking to wind and solar to secure their future

New England farmers say their future, and their succession plans, depend on their ability to…

17 August 2026

Victoria Coalition says it may keep old coal clunkers running, and will scrap plans to move away from gas

Victoria's Coalition is not ruling out coal extensions and is "throwing open the door" to…

17 August 2026

Wind farm dumped from Australia’s first pumped hydro project in 40 years – due to rocky terrain

Plans to add more solar and a wind farm to delayed pumped hydro project abandoned,…

17 August 2026

We’re trying to win a drag race with the handbrake on: Here are three reforms to deliver the energy transition

Supercharging Australia’s energy system was always going to be complex. But complexity does not need…

17 August 2026