Renewables

RES 100MW solar farm approved after years-long fight with locals

Published by

Plans for a $120 million, 100-megawatt solar farm in the NSW Southern Tablelands have been approved despite hundreds of complaints from locals that it would be an eyesore, clog up the roads, take up good agricultural land and damage the local biodiversity.

The project, run by renewables developer RES, will occupy 470 acres in the Yass Valley, seven kilometres from Sutton. Residents of Sutton made up the bulk of complainants.

The approval comes more than two-and-a-half years after the proposal first went up for community consultation in 2018.

The NSW Independent Planning Commission approved the project on Friday, saying on balance it was in the public interest. But it said the project would have to meet a number of conditions to address community concerns.

They include establishing a 60-hectare Golden Sun Moth conservation area, measures to protect the habitat of the Superb Parrot and the Legless Lizard, and meeting “setback and vegetation screening requirements to minimise visual impacts on nearby residents”.

The consultation received 231 submissions from individuals, the majority of which objected to the proposal.

“I believe this is class two agricultural land of superior quality and of limited supply within Australia. 47 per cent of Australia is made up of non-agricultural land, therefore it seems nonsensical to take up 850 acres of agricultural land for such facilities. This high quality land is worthy of protection and retention for agricultural purposes because of its state and regional importance,” wrote one local resident.

“I am horrified at the proposed level of traffic including heavy vehicles that will be filing past my front door at all hours of the day, six days a week starting very early in the morning. The noise of this traffic and the continual use of compression braking of the heavy vehicles will be unacceptable,” wrote another.

“The visual impact of an 850 acre solar farm will be significant to locals and visitors to the region. Screening of such a large site is impossible given the rolling nature of the surrounding terrain,” wrote one.

It was also opposed by local Traditional Owners who said it “failed to adequately acknowledge the Cultural Significance of the project’s area to our people”.

In its 30-page decision, the IPC answered these concerns in detail but concluded that the benefits outweighed the costs.

“The Commission finds that on balance … the impacts are acceptable and capable of being appropriately mitigated through the measures required under the conditions of consent imposed by the Commission. The Commission is of the view that the project is in the public interest,” the IPC said.

James Fernyhough is a reporter at RenewEconomy. He has worked at The Australian Financial Review and the Financial Times, and is interested in all things related to climate change and the transition to a low-carbon economy.

James Fernyhough

James Fernyhough is a reporter at RenewEconomy. He has worked at The Australian Financial Review and the Financial Times, and is interested in all things related to climate change and the transition to a low-carbon economy.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024