Renewable and battery developers hope new connection rules will eliminate delays and cost blowouts

Published by

A new set of rules on the connection process for new wind, solar and battery projects – the subject of numerous delays, cost-blowouts and tensions between developers and contractors – has been unveiled by the energy market rule maker.

The new rules follow almost four years of consultation and discussion between the energy industry and the Australian Energy Market Operator about streamlining the so-called R1 registration process, a constant source of frustration for the renewable industry.

The Clean Energy Council submitted a proposed rule change more than 12 months ago, and after a draft ruling was released this year, the final ruling has been unveiled by the Australian Energy Market Commission that it says should provide more clarity and a smoother process.

Renewable energy developers say they were often caught by surprise by the connection process, already described as one of the most complex in the world, supposedly because of Australia’s long and “skinny grid”, and complained they had little visibility over the reasons for certain decisions, and no avenue of appeal.

The whole connection regime, which involves AEMO, network owners and developers and contractors, have been cited as one of the major challenges for new projects.

Delays in connections often led to lost revenue and penalty payments from contractors to developers that caused some to collapse and others to exit the industry. Some projects were forced to wait for years to get their connection approvals. Some are still waiting.

“The proposed rule change …. will lower investment costs through reduced risk premiums, which will flow through to lower wholesale prices,” the CEC wrote in its submission last May. “Speeding up the connection of new generation
will also help manage reliability risks.”

The AEMC on Thursday said there was a lack of clear obligations and timeframes in the connections process, and the new rules address those issues by imposing timeframes and more certainty, and introducing more transparency into the whole process.

“With nearly 600 renewable energy generation and storage projects currently in the connection queue, it is critical that we speed up the process without compromising system security,” AEMC chair Anne Collyer said in a statement.

“The final rule will help bring safe, clean and more affordable electricity to Australian homes and businesses sooner. It also aims to create greater certainty for the future clean energy investors that are needed to reach the nation’s emissions reduction targets.”

Some of the changes since the draft rule was released include the requirement that new information must be included in the registration information resource and guidelines to provide connection applicants with greater certainty as to when and how AEMO and NSPs conduct their R1 assessments.

Another is a new 60 business day timeframe for AEMO to either provide an update to the connection applicant as to the status of its assessment, or to inform the applicant that it is ready to proceed to registration.

The new rules will also allow AEMO to conditionally register generators, subject to AEMO consulting on when this may be appropriate through its registration information resource and guidelines.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest publicly owned wind farm gets federal green tick to go ahead in Queensland

Australia's biggest publicly owned wind farm has been cleared for construction in Queensland coal country…

20 February 2026

Energy Insiders Podcast: How industry, AI and data centres are reshaping demand

GridBeyond CEO Michael Phelan on how industrial loads and data centres are being orchestrated by…

20 February 2026

Australian home battery upstart banks “strategic investment” towards manufacturing plans

Perth-based energy storage and off-grid energy system specialist secures a new private equity investor to…

20 February 2026

Can all solar homes become smart energy hubs? On paper – absolutely! IRL, a few hurdles remain

A South Australian trial to turn homes into grid-responsive energy hubs is now 100 households…

20 February 2026

Plan for Australia’s biggest solar-battery hybrid, with eight hours storage, get federal green tick

Plans for one of Australia's biggest solar-battery hybrid projects have been waved through the federal…

20 February 2026

AI + energy: Monster child of Origin and Facebook – or a smart, decentralised grid?

Will AI’s growing role in the grid democratise clean energy, or simply shift power from…

20 February 2026