Renewable and battery developers hope new connection rules will eliminate delays and cost blowouts

Published by

A new set of rules on the connection process for new wind, solar and battery projects – the subject of numerous delays, cost-blowouts and tensions between developers and contractors – has been unveiled by the energy market rule maker.

The new rules follow almost four years of consultation and discussion between the energy industry and the Australian Energy Market Operator about streamlining the so-called R1 registration process, a constant source of frustration for the renewable industry.

The Clean Energy Council submitted a proposed rule change more than 12 months ago, and after a draft ruling was released this year, the final ruling has been unveiled by the Australian Energy Market Commission that it says should provide more clarity and a smoother process.

Renewable energy developers say they were often caught by surprise by the connection process, already described as one of the most complex in the world, supposedly because of Australia’s long and “skinny grid”, and complained they had little visibility over the reasons for certain decisions, and no avenue of appeal.

The whole connection regime, which involves AEMO, network owners and developers and contractors, have been cited as one of the major challenges for new projects.

Delays in connections often led to lost revenue and penalty payments from contractors to developers that caused some to collapse and others to exit the industry. Some projects were forced to wait for years to get their connection approvals. Some are still waiting.

“The proposed rule change …. will lower investment costs through reduced risk premiums, which will flow through to lower wholesale prices,” the CEC wrote in its submission last May. “Speeding up the connection of new generation
will also help manage reliability risks.”

The AEMC on Thursday said there was a lack of clear obligations and timeframes in the connections process, and the new rules address those issues by imposing timeframes and more certainty, and introducing more transparency into the whole process.

“With nearly 600 renewable energy generation and storage projects currently in the connection queue, it is critical that we speed up the process without compromising system security,” AEMC chair Anne Collyer said in a statement.

“The final rule will help bring safe, clean and more affordable electricity to Australian homes and businesses sooner. It also aims to create greater certainty for the future clean energy investors that are needed to reach the nation’s emissions reduction targets.”

Some of the changes since the draft rule was released include the requirement that new information must be included in the registration information resource and guidelines to provide connection applicants with greater certainty as to when and how AEMO and NSPs conduct their R1 assessments.

Another is a new 60 business day timeframe for AEMO to either provide an update to the connection applicant as to the status of its assessment, or to inform the applicant that it is ready to proceed to registration.

The new rules will also allow AEMO to conditionally register generators, subject to AEMO consulting on when this may be appropriate through its registration information resource and guidelines.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Daytime wholesale power prices are heading to zero – isn’t that good news?

A new low proposed for solar feed-in tariffs is bound to spark consumer outrage and…

13 January 2025

Big win for Fortescue as massive 800 MW wind farm gets federal green light

Huge Fortsecue-owned wind farm wins federal environmental approval, subject to conditions, to go ahead as…

13 January 2025

Warradarge wind farm to add another 30 turbines, take lead as ‘state’s largest’

One of Western Australia's largest wind farms is set to become its largest, with the…

13 January 2025

Solar duck sends rooftop feed-in tariff close to zero. Is this the new normal?

Regulator proposes sending state's flat-rate feed-in tariff for rooftop solar to a new low barely…

13 January 2025

Grid Connections 2025: Who’s going where in Australia’s energy transition

People movements at OpenSolar, EV Council, Ørsted, Shell, Pacific Energy, Hydro Tasmania, Vestas and Energy…

12 January 2025

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025