Transmission

Regulator takes extra time to weigh VNI West dispute as tractor protest heads to town

Published by

The complexity and controversy dogging the VNI West transmission project is back on display this week, with the Australian Energy Regulator revealing it will need more time to decide on a dispute to the proposed design of the huge grid upgrade.

The $3.3 billion project is one of the more controversial parts of the Australian Energy Market Operator’s 30-year planning blueprint, attracting criticism from affected communities over visual and environmental impacts and economists and analysts over whether it offers best value for money and integration of renewables.

AEMO and Transgrid in May set out their latest plan for the new 500kV double circuit transmission line that will start on the north west outskirts of Melbourne and stretch over 800km to Wagga Wagga in the south west of NSW, via Bulgana, Kerang and Dinawan in Victoria.

The new route, which the proponents say will support upwards of 3.4GW of renewables capacity across Murray River REZ and Western Victoria REZ, did not appease critics.

And in June, a notice of dispute challenging the methods used by AEMO Victoria Planning and Transgrid was submitted to the AER by one of VNI West’s most vocal opponents, the Moorabool and Central Highlands Power Alliance.

The AER said on Wednesday that it will extend the timeframe for a decision on the matter from the usual 40 calendar days to 100, adding up-to 60 days extra time “due to the complexity of the issues” raised in the eight-page notice of dispute from MCHPA.

“Among other grounds … MCHPA considers AVP and Transgrid did not comply with NER provisions concerning the identification of credible options and selection of preferred option in the VNI-West PACR,” AER says in the notice on Wednesday.

“The AER is now due to make a determination no later than 4 October 2023. However, the AER is endeavouring to determine the dispute as soon as possible,” it adds.

In the meantime, the MCHPA will take its protest against VNI West to the streets of Melbourne next week, in the form of the Stop The Towers Tractor Rally to Spring Street.

The groups is organising the rally for Tuesday August 15, when it plans to convey the message to the Andrews Labor government “that we will not stand by and allow the destruction of our homes, farms, communities and environment.”

We need as many people and tractors as possible to really make a statement!,” the group’s Facebook page said on Tuesday.

“We have organised buses to help take the stress out of getting you to the steps of parliament.”

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: VNI West

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024