“Reduced appetite for solar:” Giant hybrid project slashes PV component by half as it seeks green tick

Published by

The developer of what was once touted as the biggest solar-battery hybrid project to gain grid connection approval in Australia has slashed the PV component in half as it seeks to gain a federal green tick for its proposal.

The UK-based Elements Green announced last year that it had gained formal technical clearance for grid connection for its Eurimbula project near the industrial and port city of Gladstone, in Queensland, which it regards as its Australian flagship project.

The project comprised two 348 megawatt (MW-dc) solar PV components – supplied by SMA – and two 333 MW (2Hr, or 666 MWh) grid-forming battery components, which the company said at the time made it the largest hybrid project in the country to achieve AEMO 5.3.4A connection approval.

“Securing the 5.3.4A letter brings us significantly closer to breaking ground this year,” Toby Roberts, the country director Australia at Elements Green, said in a statement in June.

That “breaking ground” has not yet happened, as the project has yet to gain approval under the federal government’s EPBC process. And now the company says the project will be cut in half, in terms of solar capacity and footprint, which it hopes will help with its environmental approvals.

“Commercial discussions with industry counterparts have highlighted a reducing appetite for contracting for solar-based energy,” it says in an application to the EPBC for a variation of the proposal.

“EPCo (Eurimbula Project Co) still consider the solar to be an essential part of the project, however the reduction in size / solar arrays, reduces potential negative views held with regard to the large size of the project.

The company says the revised proposal reduces the proposed land disturbance disturbance to 545.4 hectares, down from 1,173 ha, with a corresponding reduced impact on threatened species and ecological communities.

“EPCo has listened to the concerns voiced in the community and reduced the project footprint to minimise impacts on MNES (Matters of National Environmental Significance) as far as possible.

Elements Green also notes that the reduced capital required to complete the project under the revised layout will also help the project secure appropriate finance to achieve completion.

The area around Gladstone has become a hot-bed for solar and solar-battery projects, all keen to tap into the huge energy demands of the city’s smelters and refineries, and other big industry, particularly with the ageing Gladstone coal fired power generator due to close in early 2029.

These include projects already with a contract to supply Rio Tinto’s smelter and refineries, including the gigawatt scale Upper Calliope solar project, and the Smoky Creek and Guthrie’s Gap solar-battery hybrids (totalling 600 MW, and 2,400 MWh).

See Renew Economy’s Big Battery Storage Map of Australia for more information.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Buyer Beware: Carbon credit platforms repeating ills of the past

Claims and promises of carbon offset schemes are falling deep into the category of being…

23 January 2026

“Total transformation of the Australian summer:” Climate change made January heatwaves five times more likely

Australia has just experienced its worst heatwave in six years but it's set to become…

23 January 2026

Shared solar: Labor’s “free power” plan to have daily cap to stop abuse by EV and home battery owners

There will be daily cap on the federal government's Shared Solar free power offer, to…

23 January 2026

“Tallest, Mightiest and Widest:” Fortescue’s unique wind tech sees 30 pct cost savings over traditional towers

Fortescue wind technology company says its turbines will be the "tallest, mightiest and the widest,"…

23 January 2026

Biggest battery on standby as rooftop PV sets stunning new records, meeting 117 pct of state demand

Rooftop solar reaches remarkable 117 pct of state demand in Australia's most advanced renewable state,…

23 January 2026

Third battery project seeks approval in Collie, with a solar farm, even as coal mine subsidies extended

A third battery project in coal centre of Collie seeks federal green tick, as state…

23 January 2026