Redflow gets green light to supply 15MWh battery for California microgrid

Published by

Australian flow battery maker Redflow has the go-ahead to start making batteries for the solar-storage Paskenta Racheria microgrid project in California, although on a smaller basis than originally contracted for.

The Brisbane-based company will make 15 MWh of “energy pods” after receiving the order from project developer Faraday Microgrids.

The contract is worth about $US9.23 million ($A14.15 million) in revenue.

The project itself was originally slated to be a 20 MWh storage system combined with 5 MW of solar, to provide power to the sovereign Native American nation of Paskenta Band of Nomlaki Indians in Northern California, but it was cut back to 15.4 MWh after delays. 

Redflow, which won the initial contract in June last year, says the agency funding the project, the California Energy Commission (CEC) is looking for new sources of funding so the final installation can remain true to the original 20 MWh plan.

As well as being one of the biggest deployments of this type of technology in the world, the project is the company’s second largest single sale and deployment of its batteries, yet.

“This represents a major milestone for Redflow’s growth in North America and is an exciting time for us as we begin production of the batteries for our largest project to date,” said Redflow CEO and managing director Tim Harris.

Redflow expects shipment of the batteries to occur in late 2024, with installation and commissioning occurring in early 2025. 

Contracts outpacing manufacturing capacity

Redflow has signed contracts to supply slightly more than 60 MWh of batteries since June last year and is one of a small number of non-lithium storage providers who the CEC is working with to help one commercialisation and large-scale validation.

The largest contract is the 34.3 MWh project for the Valley Children’s Hospital in Madera, California, to switch from diesel generators, and is also being led by Faraday Microgrids.  

Those batteries are due in 2025. 

The smallest is a 200 kWh project with Acciona in Spain.

Other projects signed in this financial year are a 4 MWh battery in Ipswich for Energy Queensland and a 1.2-1.4 MWh battery for the US Department of Defence. 

This month Redflow signed a fourth contract supported by California Energy Commission (CEC) funding, to supply its zinc-bromine battery technology to the Barona Band of Mission Indians.

The $20.1 million project is for a 6.6 MWh battery and has been shortlisted for a $13.8 million grant through the CEC. 

Grant terms will now be negotiated with the CEC, with development expected to get underway later this year and anticipated deployment some time in 2025 or 2026.

The volume of work Redflow is signing up outpaces the company’s current manufacturing capacity in Thailand, which it had hoped to ramp to 40 MWh per annum by the end of 2023.

Instead, problems with quality of glass filled high density polyethylene material from suppliers meant production capacity was stuck around 8-10 MWh per annum.

The company says this issue has been resolved and hopes to hit its original target of 80 MWh capacity by the end of the year, however. 

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024