Renewables

Pioneering and repriced offshore wind farm gets final approval in New York

Published by

New York State has granted the 810MW Empire Wind offshore project its final approval, authorising the project to begin construction, nearly five years after it was selected in the state’s first offshore wind tender.

It has been a long and at times uncertain road for Empire Wind since winning the contract in mid-2019, with the COVID-19 pandemic and Russia’s invasion of Ukraine combining to send costs soaring to the point where original developers BP and Equinor – along with Danish wind energy giant Ørsted – questioned the project’s viability.

The consortium of companies ultimately sought to renegotiate the contract for Empire wind, with the original version no longer able to cover the cost of building and financing projects due to rising inflation and shifting material costs.

The bid to adjust the prices for power generation was rejected the New York State Public Service Commission (NYSPSC) in October 2023, a decision affecting not only Empire Wind, but also the Beacon Wind offshore wind farm and Ørsted’s 880MW Sunrise Wind project.

Ørsted similarly withdrew from the Maryland Public Service Commission orders approving the 966MW Skipjack Wind project earlier this year, explaining that the original power sales contract was “no longer commercially viable because of today’s challenging market conditions, including inflation, high interest rates and supply chain constraints.”

Things began to look up in March, however, after New York State governor Kathy Hochul awarded new contracts worth just over $US150 per megawatt-hour – almost double the original strike price – for Empire Wind and the 924MW Sunrise Wind being jointly developed by Ørsted and Eversource.

The contracts were awarded as part of a fourth renewable energy auction which gave companies a chance to rebid their projects and replace existing projects.

With these updated contracts in place, progress has moved swiftly, and the NYSPSC has now granted Empire Offshore Wind its final approval to begin construction on Empire Wind I.

The NYSPSC awarded Empire Wind its Certificate of Public Convenience and Necessity (CPCN) late last week, which authorises the construction and operation of transmission facilities for the delivery of electricity into New York from the 810MW offshore wind farm.

“Our decision today provides the last remaining approval before construction can begin on this offshore wind project, which is a high priority for the State given that it will advance the State’s renewable and clean energy goals in compliance with the Climate Act,” said Rory M. Christian, Public Service Commission chair.

“It is critical that construction begin in early May for the developer to keep the construction schedule on track and achieve the anticipated commercial operation date.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

More than 50 countries, including Australia, meet to thrash out an orderly path away from fossil fuels

Energy minister Chris Bowen is absent from talks in Colombia, but has been voicing support…

27 April 2026

Data centres drive significant boost in grid demand for Australia’s biggest energy retailer

Australia's biggest energy retailer reports a surprising 4 pct lift in electricity sales, driven by…

27 April 2026

Too big to fail? Snowy 2.0 critics predict fresh cost blowouts, while others say it’s far too late to turn back

Critics fear interest, the cost of building connecting transmission, and other fees are creating a…

27 April 2026

From footnote to feature: How batteries are evolving on the national electricity market

The question is becoming less about whether batteries matter. It is how visible, coordinated, and…

27 April 2026

“What Absolute BS:” Forrest calls out coal lobby as diesel fuel tax debate intensifies

Andrew Forrest claps back after Coal Australia accuses Fortescue of "grandstanding and virtue signalling" over…

27 April 2026

Construction contract awarded for new 200 MW, four-hour battery project

Contract awarded to build a 200 megawatt MW, 800 MWh battery energy storage system (BESS)…

27 April 2026