Renewables

Pioneering and repriced offshore wind farm gets final approval in New York

Published by

New York State has granted the 810MW Empire Wind offshore project its final approval, authorising the project to begin construction, nearly five years after it was selected in the state’s first offshore wind tender.

It has been a long and at times uncertain road for Empire Wind since winning the contract in mid-2019, with the COVID-19 pandemic and Russia’s invasion of Ukraine combining to send costs soaring to the point where original developers BP and Equinor – along with Danish wind energy giant Ørsted – questioned the project’s viability.

The consortium of companies ultimately sought to renegotiate the contract for Empire wind, with the original version no longer able to cover the cost of building and financing projects due to rising inflation and shifting material costs.

The bid to adjust the prices for power generation was rejected the New York State Public Service Commission (NYSPSC) in October 2023, a decision affecting not only Empire Wind, but also the Beacon Wind offshore wind farm and Ørsted’s 880MW Sunrise Wind project.

Ørsted similarly withdrew from the Maryland Public Service Commission orders approving the 966MW Skipjack Wind project earlier this year, explaining that the original power sales contract was “no longer commercially viable because of today’s challenging market conditions, including inflation, high interest rates and supply chain constraints.”

Things began to look up in March, however, after New York State governor Kathy Hochul awarded new contracts worth just over $US150 per megawatt-hour – almost double the original strike price – for Empire Wind and the 924MW Sunrise Wind being jointly developed by Ørsted and Eversource.

The contracts were awarded as part of a fourth renewable energy auction which gave companies a chance to rebid their projects and replace existing projects.

With these updated contracts in place, progress has moved swiftly, and the NYSPSC has now granted Empire Offshore Wind its final approval to begin construction on Empire Wind I.

The NYSPSC awarded Empire Wind its Certificate of Public Convenience and Necessity (CPCN) late last week, which authorises the construction and operation of transmission facilities for the delivery of electricity into New York from the 810MW offshore wind farm.

“Our decision today provides the last remaining approval before construction can begin on this offshore wind project, which is a high priority for the State given that it will advance the State’s renewable and clean energy goals in compliance with the Climate Act,” said Rory M. Christian, Public Service Commission chair.

“It is critical that construction begin in early May for the developer to keep the construction schedule on track and achieve the anticipated commercial operation date.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

What fossil madness is this? Wars can’t interrupt flow of wind and the sun, but all we hear is drill, baby, drill

Australia is in the grip of a global fossil fuel crisis. It knows it has…

20 March 2026

Can Australia make its own wind turbine parts? Global giant suggests it might be at the whim of federal LNP

CEO of global wind giant says bipartisan agreement needed if local manufacturing is to be…

20 March 2026

Why some of Australia’s energy market conventions should go the way of the dinosaurs

We face some big challenges. To what extent should we protect businesses designed to operate…

20 March 2026

In the case of critical minerals, China did not take our lunch – we left it on the table

Australia needs to apply a new lens of green energy and industry statecraft, including developing…

20 March 2026

Energy Insiders Podcast: Why batteries are the answer to nearly everything

We talk to Jeff Monday from Fluence on the fall in battery costs and the…

20 March 2026

Independent panel approves gigawatt scale battery three months after local opponents force referral

Independent Planning Commission gives approval to gigawatt-scale standalone battery project just three months after it…

20 March 2026