Danish wind energy giant Ørsted has piloted a new low-noise installation method for offshore wind turbine monopile foundations which the company believes “represents one of the greatest advancements yet in offshore wind foundation installation methodology.”

Ørsted successfully tested the new installation method on three monopile foundations during construction at the 253MW German offshore wind farm Gode Wind 3.

According to Ørsted, the noise mitigation method involves a “patented jetting technology attached to the monopile, which lowers the resistance of the surrounding sandy soil, effectively allowing the foundation to sink into the seabed – completely replacing conventional installation methods such as pile driving.”

The water jetting technology employs high-pressure water jets attached to the monopile to disturb the sandy seabed, minimising the resistance as the monopile is sunk into the ground.

Image Credit: Ørsted

A new monopile installation method may sound a strange contender for “one of the greatest advancements yet in offshore wind foundation installation methodology” but, as more and more offshore wind farms are built around the globe, ensuring the environmental stability of the surrounding ecosystems becomes increasingly vital.

Traditional installation methods such as pile driving create significant disturbances as the massive steel pipes are hammered into the seabed to serve as a foundation for the turbine.

The repetitive and blunt-forced nature of pile driving creates audible reverberations that can disorient and harm local wildlife, as well as physically disturbing the seabed.

Ørsted claims that the implementation of their new installation technology results in a substantial decrease in underwater noises, with a reduction of 34 decibels relative to commonly used installation methods.

Moreover, and without additional mitigation, noise levels using the new installation method were reduced by over 99 per cent to a level “just marginally above the ambient noise found in the German Bight in the North Sea.”

It is also hoped that, once adopted at scale, this new installation technology will allow for more efficient and cost-effective installations of offshore wind farms.

Image Credit: Ørsted

“Ørsted has been at the forefront of offshore wind innovation and marine protections for 30 years, and we continue to push the envelope on new innovative solutions,” said Patrick Harnett, executive vice president and chief operating officer at Ørsted.

“This new technology is a potential game changer for how we build offshore wind.

“Once industrialised, it could not only be cheaper, faster, and far quieter – without additional mitigation – than any other monopile installation technology, it also has the potential to make next-generation foundations lighter as they won’t need to be designed for conventional installation process.” 

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

From niche technology to 500,000 households “taking control:” Cheaper Home Batteries hits half-million milestone

The number of Cheaper Home Batteries installations has passed the half-million mark, a huge new…

13 August 2026

Researchers “froth” over new solar recycling method that recovers 99 pct of silver from used panels

A new take on a widely used mining technique called froth flotation can recover "virtually…

13 August 2026

Power plays: Tomago’s big green switch, the Big 3’s lack of ambition, and why Snowy must change its stripes

From the country's biggest energy utilities announcing their profits and outlook, to the country's biggest…

13 August 2026

Edify Energy reaches financial close on another pair of solar and battery hybrid projects

Edify Energy reaches financial close on another pair of solar and battery hybrid projects, in…

13 August 2026

What five Fijian sparkies taught me about remote, off-grid solar and battery systems

When it comes to remote solar and battery storage solutions, the knowledge you leave behind…

13 August 2026

Tomago won’t be 100 pct renewable until 2033, but Squadron and others want to see multiple supply deals

It will take at least six years to make Australia's largest aluminium smelter 100 per…

13 August 2026