Coal

Australia’s biggest coal plant can’t get enough coal, as fossil fuel disaster accelerates

Published by

The fossil fuel crisis affecting Australia’s energy markets took a new twist on Wednesday when Origin Energy, the owner of the country’s biggest coal generator, confirmed it could not source enough coal to keep the  2.8GW Eraring plant in NSW operating at anywhere near full capacity.

The supply problems add to the soaring coal and gas prices, and coal plant outages, that have driven the electricity markets, and analysts, crazy in the past few weeks, resulting in the collapse of some energy retailers, “house full” signs on others, and skyrocketing bills for consumers.

See: “Sorry, we can’t help today:” Energy retailers turn away customers in face of crazy prices

In its quarterly update, Origin confirms its view that the price rises were being driven by coal plant outages and high fossil fuel prices, and warns it will continue in at least the near term until more renewables can be brought into the grid.

“The challenges with coal delivery to Eraring Power Station are expected to persist into FY2023,” it says in its quarterly update.

“This is expected to result in a material increase in coal purchasing costs given high coal prices and continued exposure to high spot electricity prices.

“While Origin has worked closely with coal suppliers to secure additional coal supply by rail, there are limitations to the amount of coal that can be delivered to the plant by this method.Therefore, there is uncertainty regarding the plant’s output in FY2023.”

The news will be of huge concern to energy market authorities, who fear that other coal fired power stations will be similarly challenged, apart from possibly the brown coal generators in Victoria that can dig up the dirt in their backyard.

The future of those plants is now under question, although it is clear that tech billionaire Mike Cannon-Brookes, who has scored a stunning victory in seeking to change the coal-burning strategy of AGL, knows that new renewables and storage are an absolute priority before any more closures.

But the situation also underlines the fragility of a power system that has been so dependent on dirty fuels, unreliable and ageing plants, and now crippling coal costs and supply shortages.

See: Australia’s electricity markets are on crack: It’s time to do something

The issue with Origin seems to be specific to the supply problems with the Mandalong mine, compounded by limited rail access and supply chain issues. But it just adds to the vulnerability of relying of ageing fossil fuel technologies in a dramatically changing environmental and financial environment.

Queensland coal fired power stations have also suffered from floods, which has caused supply issues because coal can no longer be delivered by rail, and have to be done by truck.

It adds to the unfolding disaster left by the Coalition government and the previous energy minister Angus Taylor, who had no interest in smoothing the transition to green energy and instead erected policy bollards and committed billions to fossil fuel industries.

Australian industry and consumers will be paying the cost of this disaster for years. The energy market is now considered to be out of control, with all the usual financial hedges proving useless in a market where the cost of so called “baseload” is now more than that of generating power from diesel.

Energy analysts have been warning of this looming disaster for years, although they could not have predicted how quickly it would be accelerated by events overseas, including the Covid19 pandemic and Russia’s invasion of Ukraine.

Origin says market volatility will continue, while its own earnings will be balanced out by a windfall from the sales of gas and LNG at extraordinarily high prices, offset by the increased cost of coal generation.

It says Eraring has been facing supply challenges throughout the current financial year, and it has deteriorated in recent weeks, with one of its main suppliers, Centennial Coal, warning of “further constraints associated with geological features at its Mandalong mine.”

The delivery shortfall amounts to around one million tonnes this financial year, but interruptions will continue for the rest of this calendar year, a situation made worse by delays in equipment supply, which is stopping Centennial from immediately addressing the problems in the mine.

It has forced Origin to go into the market for new coal supplies, at a time when it is difficult to source and where the costs for what can be sourced are substantial.

“The recent material under-delivery of coal to Eraring results in lower output from the plant, additional replacement coal purchases at significantly higher prices, and is being exacerbated by coal delivery constraints via rail,” Origin says.

“In addition, the lower output from Eraring results in a greater exposure to the purchase of electricity at current high spot prices in order to meet customer demand.”

As a result, Origin now expects its underlying earnings from the energy markets division this financial year to range from $310 million to $460 million, lower than the original guidance range of $450 – $600 million.

The supply problems for Eraring, the high cost of coal and the exposure to high spot electricity prices, will continue into the next financial year and despite an expected windfall from its gas operations it has dropped all profit guidance for the coming year.

“Origin will continue to assess the outlook, with a view to providing an update at (our) full year results in August,” it says.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Another three big wind and battery projects sucked into EPBC process

Another three big renewable and storage projects enter EPBC planning pipeline, with two of them…

3 February 2025

Trump’s “drill baby, drill” plan is a disaster for energy security, and prices

Lessons from Australia teach us that going all-in on fossil fuel exports is a recipe…

3 February 2025

“Huge moment:” Major push to harness home PV, batteries and EVs on world’s biggest isolated grid

WA awarded more than $20 million to create "Australia's first live DER marketplace," in race…

3 February 2025

Wind farm objections: In Germany, one group of protesters averaged 64 complaints per person

German region received 440,000 complaints against wind projects. Most came from a single group, with…

3 February 2025

“Putting fatter lines on poles:” Consultation begins on renewable zone for nation’s coal hub

Consultation begins on the first major renewable zone to seek bigger lines rather than new…

3 February 2025

Customers will take as much wind and solar as they can “because they are the cheapest,” says Brookfield

Brookfield, with $1.5 trillion in assets and now in control of Neoen, says demand and…

3 February 2025