Wind

One of Australia’s biggest and worst performing wind farms back on line after near two month outage

Published by

One of the biggest but worst performing wind farms in Australia is back on line after a seven week outage caused by a transmission failure at its substation.

The 420 megawatt (MW) MacArthur wind farm near Warrnambool in south western Victoria was once the biggest wind project in the country, and the southern hemisphere, but it has delivered poor returns in terms of output since starting full operations in early 2013.

Over the last three years it has delivered an average capacity factor of less than 20 per cent, according to data provided by Rystad Energy, less than half the best performing wind farm in the main grid, which happens to be the much smaller 31 MW Kiata wind farm to the north.

Macarthur was predicted to produce at a 35 per cent capacity factor when the project was first announced by AGL Energy in 2010, which would have equated to around 1,200 gigawatt hours a year. But it has never reached that figure and in recent years it has failed to produce more than 800 gigawatt hours a year.

Source: Rystad Energy.

It’s never been clear exactly why the wind farm has failed to deliver on expectations, with some speculation about lower than expected wind speeds, and others pointing to the layout of the turbines. It is located on flat grazing land.

The chart above, from Rystad, identifies Macarthur as having the fourth lowest capacity factor in the three years from the start of 2021 to the end of 2023. Most of the wind farms around it on that table were ramping up capacity after completing construction and connections.

The Macarthur wind farms uses 140 Vestas turbines, each sized at 3 MW and with a hub height of 85 metres. Newer turbines are at least twice the capacity and at least twice the height. But it’s not always size that counts – Kiata is consistently the best performing wind farm in the country with a turbine size of 3.45 MW.

The latest problem at Macarthur occurred in early June because of a transformer failure, said a spokesman for operator AGL. It did not return to service until late last week. The project is operated by AGL but is now owned by Palisade, Atmos and Dexus.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

State stumps up $10.8 million to help customers electrify as private gas network shuts down

State government provides funds to help homes and businesses electrify as the owner of the…

29 April 2026

US predicts stunning 80 GW increase in big solar, wind, and battery storage in next year – despite Trump

If Trump had every heard of the EIA it is likely he would have scrapped…

29 April 2026

“When can I get a job?” Community leaders say coal country ready – and waiting – for offshore wind

As conservative lobby groups continue to push for a "rethink" of Victoria's offshore wind plans,…

29 April 2026

Australia’s sliding doors moment: From “dig and ship” to trusted renewables transition partner

Fossil fuels have been exposed as the weak link in a secure economy and a…

29 April 2026

Solar Insiders Podcast: Can we make climate action great again?

Thom Woodroofe on his new book, Power, Prosperity & Planet, and why making solar as…

29 April 2026

Massive six-hour battery project seeks federal green tick for site in Victoria’s main coal hub

A massive 6-hour big battery has joined the queue for federal approvals for a site…

29 April 2026