Once too soft, now too hard: Snowy 2.0 tunnelling machine Florence comes to a stop again

Published by

The problem-plagued and controversial Snowy 2.0 pumped hydro project has hit yet another snag, with its tunnel boring machine Florence halted once again, this time because it has become wedged in hard rock.

The federal government owned Snowy Hydro – already facing massive delays and huge over-runs on costs for the project – announced this week that TBM Florence had halted operations a week ago, on Thursday, May 16.

It said TBM Florence had already slowed due to “very hard and abrasive rock” a day earlier, before “the project ceased excavation … on Thursday 16 May due to rock pinching on the machine’s shield.”

The TBM had been making slow progress in recent weeks as it cut through the hard rock at its Tantangara site, one of several drilling locations in Kosciuszko National Park.

According to ABC News, the problem arose because “Florence was mistakenly turned too sharply from a straight line into a curve, causing part of the cutting head to become wedged. Further boring compounded the problem, with the machine making only incremental movements since.”

Snowy Hydro said it had “sought immediate advice from a specialist contractor with experience at other Australian projects with the same TBM situation” and subsequently began using high pressure water jets in an effort to remove the rock “impinging on TBM Florence’s shield.”

The company says it is unsure when excavation will recommence saying only that it “will be determined on the successful removal of the rock.” It says it will provide an update next week.

The Snowy 2.0 project has blown out from an original cost estimate of around $2 billion to $12 billion – not including the cost of transmission to properly connect to the grid – and delays which have pushed the project completion out to the end of the decade.

Florence is supposed to be excavating some 16 kms of the headache tunnel but not even completed a single kilometre and has been slowed to a snail’s pace – even after finally restarting after getting bogged for months in soft soil.

ABC News suggested the situation is much more serious than has been publicly acknowledged by Snowy Hydro and could take weeks or even months before normal drilling resumes.

One source told ABC News that they had “wedged the thing in good and proper,” with another commenting somewhat more succinctly, “It’s f****d.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Chinese solar company manager accused of offering bribe to secure approval for PV panels, refused bail

A manager with a Chinese solar panel supplier appears in court on charges of attempting…

5 August 2026

First of dozens of 80 metre-long turbine blades arrives at first new wind farm in state’s main grid for years

Nearly five months after completing its final concrete pour, King Rocks wind farm has received…

5 August 2026

Bowen says coal “isn’t baseload anymore, it’s unreliable,” will stop states pushing gas for data centres

Bowen says data centres could rescue stalled renewables as he warns coal-fired power stations are…

5 August 2026

Aldi Solar heads west as it expands its PV and home battery offer across Australia

Super-affordable solar and battery offer from the German discount supermarket chain has now been extended…

5 August 2026

Mid-winter solar records tumble around the country, with more batteries to soak it up

Large-scale solar generated record high shares of electricity in every Australian state but one over…

5 August 2026

Big solar and battery project gets planning approval, on condition it paves road to minimise dust

Independent panel receives 19 new submissions on solar and battery project, but cancelled a scheduled…

5 August 2026