Policy & Planning

Ombudsman says transmission projects plagued by lack of trust in local communities

Published by

A lack of trust is characterising the rollout of transmission infrastructure in New South Wales (NSW), according to the state’s energy and water ombudsman.

The organisation had only been handling transmission issues for a little over six months before forming strong views on how the industry needs to be fixed.

Between December 1 and June 30, the ombudsman received 43 complaints about transmission projects as the state begins to build out the infrastructure needed by renewable energy zones (REZs).

Unsatisfactory community engagement practices was one of the top complaints, as was a lack of response to concerns such as failing to answer questions by a deadline, and not having phone lines set up to handle questions, and low transparency and information on proposed works.

Other complaints were around transmission line placement, worried about dust and traffic and construction disruption. 

“Trust-building is critical to the energy transition, and many people are telling us they have felt ignored during the consultation process,” the ombudsman’s annual report says. 

The ombudsman is limited to transmission issues and doesn’t yet handle complaints on renewable energy or battery storage, but the insights gleaned over slightly more than six months of working in the industry offer a useful insight as to the key pressure points for communities. 

Community consultation, population increase, how companies are going about acquiring land for transmission projects, and the consequences for communities of major infrastructure works are the four hot button issues the ombudsman identified. 

“Infrastructure entities are not reaching all members of the community, and community members do not feel there is genuine engagement, where their local knowledge is valued. Infrastructure developers may therefore not be trusted,” the annual report says.

“Some community members embrace increased populations because of the economic benefits; others are concerned that local venues, hospitals, trades and services will be overwhelmed.

“Landholders are finding the acquisition process for transmission easements stressful; concerns about tax implications and legal costs are significantly affecting some people’s mental health.

“There are concerns about changes to the landscape, reduction in productive farmland, traffic, transport, service interruptions and delays and the lack of coordination to minimise these impacts.”

The solution lies in better government coordination and regulations, the organisation said in a submission to the NSW Parliamentary inquiry on the impact of REZs on rural and regional communities and industries. 

It wants to see legally binding engagement standards that specify consultation timeframes and a requirement for all energy companies to have and promote internal and external dispute resolution processes. 

The submission said the definition of ‘affected landholders’ needs to include directly and indirectly impacted landholders and neighbours, as some developers have started doing but which is still at their discretion. 

And it endorses views long held by councils that consultation and regional planning must be coordinated, and one shared by Australian Energy Infrastructure Commissioner (AEIC) Tony Mahar that the public exhibition period for major projects should be longer, to give communities more time to educate themselves on how to respond.

f you would like to join more than 26,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Buyer Beware: Carbon credit platforms repeating ills of the past

Claims and promises of carbon offset schemes are falling deep into the category of being…

23 January 2026

“Total transformation of the Australian summer:” Climate change made January heatwaves five times more likely

Australia has just experienced its worst heatwave in six years but it's set to become…

23 January 2026

Shared solar: Labor’s “free power” plan to have daily cap to stop abuse by EV and home battery owners

There will be daily cap on the federal government's Shared Solar free power offer, to…

23 January 2026

“Reduced appetite for solar:” Giant hybrid project slashes PV component by half as it seeks green tick

Developer of what was once hailed as the biggest solar hybrid project cuts PV component…

23 January 2026

“Tallest, Mightiest and Widest:” Fortescue’s unique wind tech sees 30 pct cost savings over traditional towers

Fortescue wind technology company says its turbines will be the "tallest, mightiest and the widest,"…

23 January 2026

Biggest battery on standby as rooftop PV sets stunning new records, meeting 117 pct of state demand

Rooftop solar reaches remarkable 117 pct of state demand in Australia's most advanced renewable state,…

23 January 2026