Offshore wind project wins court appeal over rejected licence in Gippsland

Published by

One of Australia’s first offshore wind projects has been given a lifeline after a court ordered a review of its rejected bid for a key licence.

Energy Minister Chris Bowen was ordered to pay Seadragon’s legal fees after the Federal Court ruled he was wrong to knock back Flotation Energy’s application to build the Seadragon wind farm off the Victorian coast.

The minister’s office acknowledged the decision on Friday, which could act as an important test case for how feasibility licences are awarded when bids contain overlapping areas.

The earlier decision was made when Seadragon’s proposal for a licence overlapped with a different project and was deemed to be of lower merit.

Seadragon asked to be given a feasibility licence for a smaller area that didn’t include the overlap, but the energy minister knocked it back.

That was on the perceived grounds the licence could not be granted over anything other than the entire proposed area.

But Federal Court Justice Nye Perram rejected that reading of the Offshore Electricity Infrastructure Act and ordered the minister to reconsider the proposal with a correct application of the law.

The act “plainly” allowed the minister to grant the application, he said.

“The power conferred extends to ‘an area’ – any area – which meets those requirements … a reduced area to that sought by an applicant is still ‘an area’,” Justice Perram said.

The proposed Seadragon wind farm was to include up to 150 wind turbines and a network of subsea cables off the coast of Gippsland.

It involved wind turbine generators on fixed foundations installed between 20 and 40km off Ninety Mile Beach between Paradise Beach and McGaurans Beach, on Bass Strait.

A spokeswoman for the minister said he would review the judgment before taking further steps on the application.

“Establishing Australia’s offshore wind industry is a complex but critical step in decarbonising our energy market,” she said.

“Government and industry alike have an interest in regulatory certainty and that is what this process in the Federal Court is about.”

The Seadragon project was due to begin construction in 2028 with an expected operational date of 2030.

Offshore wind forms a large part of Australia’s plans to net-zero emissions by 2050.

AAP

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026