Offshore wind farm linked to green hydrogen electrolysers wins auction with zero subsidy

Published by

The Dutch government has selected a zero-subsidy bid by Oranje Wind Power II to build the 760MW Hollandse Kust (west) offshore wind farm in the Dutch North Sea, which will include 600MW of onshore electrolysers for the production of green hydrogen.

The 760MW Hollandse Kust (west) Wind Farm Site VII is one of two new offshore wind farms due to become operational in the Dutch North Sea in 2026.

The Netherlands Enterprise Agency (RVO) announced late last week that Oranje Wind Power II, a subsidiary of German energy giant RWE, had been awarded the contract to build the 760MW offshore wind farm.

The bid, which required no government subsidy, will also include additional functionality. Among the plans is the development of 600MW of onshore electrolysers to produce green hydrogen, 225MW of e-boilers for district heating and industrial applications, batteries, and even a floating offshore solar energy plant.

Set to be located 50km off the coast of the Netherlands, Site VII will be located alongside Site VI in the growing Hollandse Kust (west) Wind Farm Zone, which upon development will boast capacity of 1.4GW.

“This new wind farm is another major step in making the Netherlands more sustainable,” said Rob Jetten, Netherlands’ minister for climate and energy.

“Wind energy is also very important for companies and industry that are increasingly electrifying their installations, replacing fossil fuels and raw materials,” Jetten said.

“With this project we are making another concrete step towards achieving the goal of 21GW of offshore wind energy around 2030.”

Energy to power one million homes

The original announcement from the RVO claimed that the offshore wind farm would house capacity of 700MW, but subsequent information from RWE confirms that capacity will be 760MW.

“Hollandse Kust West VII will seriously contribute to the energy transition by producing green electricity for almost one million Dutch homes,” said RWE CEO Markus Krebber.

“With our innovative concept we developed a blueprint for a new generation of offshore wind farms, which can be perfectly integrated into the energy system.”

European wind energy trade body WindEurope says the winning project provides further proof of using qualitative, non-price criteria. Instead, the qualitative criteria measures how well the wind farm will be integrated into the country’s energy system.

“It’s great the Dutch made so much use of non-price section criteria in their latest offshore wind auction.” said Giles Dickson, WindEurope CEO. “And it’s worked!

“They’ve shown you can get away from price-only auctions – and select a winner with measurable and objective non-price criteria, in this case on system integration.”

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024