Numurkah solar farm, to help power steel works, Melbourne trams, begins production

Published by

Neoen Australia’s Numurkah solar farm has begun sending power to Victoria’s grid, making good on landmark deals to power both the Laverton steel works and Melbourne’s network of trams.

The $198 million facility – rated at 100MW (AC), making it the largest in the state to date – kicked off generation right on schedule on May 7, as is illustrated by the chart below  provided by Paul McArdle from Global Roam, the providers of our popular NEM-Watch widget.

As we reported here, the construction of the project near Shepparton in the Goulburn Valley, was underpinned by a ground-breaking deal signed with Sanjeev Gupta’s GFG Alliance.

Prior to that, it had also signed a deal with the Victorian government for the supply of renewable energy certificates towards its tram network.

The project was also significant for marking the achievement of the first Gigawatt of projects in Australia for French developer Neoen – counting those projects both under construction or in operation. Neoen also owns the Tesla big battery in South Australia, which they officially refer to as the Hornsdale Power Reserve.

As Neoen Australia chief Franck Woitiez put it at the time, the project – in partnership with Gupta’s SIMEC Zen Energy – has also served to prove “that collectively, we are moving towards our aim of delivering sustainable, reliable and competitive energy to all Australians.”

The Clean Energy Finance Corporation, which is provided $56 million in loans towards the project, described it as a “path-breaking example of how solar energy can deliver a cost-effective solution for Victoria’s energy-intensive manufacturers.”

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024