Nuclear plant trips due to fire, and battery storage steps in to stabilises the grid

Published by

What happens when a giant nuclear power station suddenly goes off line? It’s a question that market operators have to ask themselves all the time, and one that the Coalition might want to put should its fanciful nuclear plan every come to pass.

The biggest units on the grid are generally nuclear, in those countries that have them, and a considerable amount of planning and expense needs to make sure that the back-up is on hand, despite the insistence by some of the whackier pro-nuclear spruikers in Australia that no storage or gas is needed.

The biggest unit in the Australian grid is the 750 megawatt (MW) Kogan Creek coal fired power station in Queensland. Nuclear units are often nearly twice the size, and last week a 1,322 MW unit at the South Texas nuclear facility suddenly tripped due to a fire in the switchyard.

According to Grid Status, which monitors grid operations in the US, the frequency excursion was arrested by a rapid response from the state’s rapidly growing portfolio of big battery projects.

“Immediately, grid frequency declined,” Grid Status noted in a post on LinkedIn and X. “An excursion below critical levels required a fast response by ERCOT to ensure stability of the grid. In this case, ERCOT swiftly deployed ancillary services, including a significant amount of batteries providing ECRS, to boost the frequency back to normal.”

ERCOT is the Electricity reliability Council of Texas, which manages the grid. ECRS refers to the contingency reserve service.

The big batteries were back in action a few days later when one of the state’s coal fired power station units also tripped.

Texas is expected to more than double its battery storage capacity in 2024, adding around 6.4 GW of battery capacity (with varying levels of storage), to the 5.5 GW that existed before.

The response of the battery capacity to the nuclear trip underlines the fact that all forms of energy generation need back up – whether it be for lulls caused by weather conditions or by sudden or planned losses of large amounts of capacity due to unexpected trips, storms, fires or maintenance.

In nuclear dominated Ontario, where more than half of electricity generation is sourced from nuclear, two of the world’s biggest batteries are being built to help even out supply and demand.

One of those batteries will be built by Neoen, and it has been contracted to store energy in the middle of the day – when the output of nuclear is often surplus to requirements – and reinject it into the grid in the evening peaks. It has a similar contract in Western Australia to soak up solar, rather than nuclear, in the middle of the day.

It’s interesting to note that when the Texas nuclear plant tripped – it is still out of action 10 days later – the usual pro-nuclear tried to blame the ramp up of rooftop solar, even though rooftop PV hadn’t actually ramped up at that stage.

Those claims were nonsense of course, as are many of their claims. The fire was confirmed by the US Nuclear Regulatory Commission, which said it occurred in the switchyard and was put out within two hours on July 23. There were no further impacts. The nuclear unit still has not resumed operations.

For a whole bunch of reasons, nuclear is not always on. Just like any other form of generation, you need back up and a plan B.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New England locals force huge battery project proposal to go before independent panel

Locals who say they overwhelmed by three neighbouring big battery projects force one gigawatt proposal…

13 January 2026

State government allows all five turbines to be built in small wind project

Developer of small wind project in Victoria gets approval for five turbines from state government,…

12 January 2026

Massive 2 GW wind, solar and battery project lands all state planning approvals in breathtaking four months

The wind, solar and battery project secured state and EPA approvals in an astonishing four…

12 January 2026

Solar installer fined $9,000 over unsafe home battery installations, including one that sparked fire

A solar installer has been fined for unsafe home battery installations, including one that sparked…

12 January 2026

Victoria gives green light to contested wind project, with fewer turbines and operating limits

A 600MW wind project has the green light to start construction, but government wants turbine…

12 January 2026

Another two big solar and battery projects sent to independent panel by long distance objectors

Another two major solar and battery projects have been referred to independent commission after objections…

12 January 2026