What happens when a giant nuclear power station suddenly goes off line? It’s a question that market operators have to ask themselves all the time, and one that the Coalition might want to put should its fanciful nuclear plan every come to pass.

The biggest units on the grid are generally nuclear, in those countries that have them, and a considerable amount of planning and expense needs to make sure that the back-up is on hand, despite the insistence by some of the whackier pro-nuclear spruikers in Australia that no storage or gas is needed.

The biggest unit in the Australian grid is the 750 megawatt (MW) Kogan Creek coal fired power station in Queensland. Nuclear units are often nearly twice the size, and last week a 1,322 MW unit at the South Texas nuclear facility suddenly tripped due to a fire in the switchyard.

According to Grid Status, which monitors grid operations in the US, the frequency excursion was arrested by a rapid response from the state’s rapidly growing portfolio of big battery projects.

“Immediately, grid frequency declined,” Grid Status noted in a post on LinkedIn and X. “An excursion below critical levels required a fast response by ERCOT to ensure stability of the grid. In this case, ERCOT swiftly deployed ancillary services, including a significant amount of batteries providing ECRS, to boost the frequency back to normal.”

ERCOT is the Electricity reliability Council of Texas, which manages the grid. ECRS refers to the contingency reserve service.

The big batteries were back in action a few days later when one of the state’s coal fired power station units also tripped.

Texas is expected to more than double its battery storage capacity in 2024, adding around 6.4 GW of battery capacity (with varying levels of storage), to the 5.5 GW that existed before.

The response of the battery capacity to the nuclear trip underlines the fact that all forms of energy generation need back up – whether it be for lulls caused by weather conditions or by sudden or planned losses of large amounts of capacity due to unexpected trips, storms, fires or maintenance.

In nuclear dominated Ontario, where more than half of electricity generation is sourced from nuclear, two of the world’s biggest batteries are being built to help even out supply and demand.

One of those batteries will be built by Neoen, and it has been contracted to store energy in the middle of the day – when the output of nuclear is often surplus to requirements – and reinject it into the grid in the evening peaks. It has a similar contract in Western Australia to soak up solar, rather than nuclear, in the middle of the day.

It’s interesting to note that when the Texas nuclear plant tripped – it is still out of action 10 days later – the usual pro-nuclear tried to blame the ramp up of rooftop solar, even though rooftop PV hadn’t actually ramped up at that stage.

Those claims were nonsense of course, as are many of their claims. The fire was confirmed by the US Nuclear Regulatory Commission, which said it occurred in the switchyard and was put out within two hours on July 23. There were no further impacts. The nuclear unit still has not resumed operations.

For a whole bunch of reasons, nuclear is not always on. Just like any other form of generation, you need back up and a plan B.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Neighbours of giant wind project offered up to $100m in unique deal that could shape design

Near neighbours of one of the country's biggest wind projects are being given the opportunity…

31 January 2025

Farmers offered $300m in discount loans for solar, batteries, EVs, seaweed and windbreaks

Farmers offered up to $300 million of discount loans to help efforts to cut emissions,…

31 January 2025

Biggest vanadium flow battery in Australia promised for ailing Kalgoorlie grid

A 500 MWh vanadium flow battery - the biggest in Australia - has been promised…

30 January 2025

Big batteries cash in as they charge past gas to become second biggest player in evening peaks

The growth of big battery projects - fuelled by falling costs and growing needs -…

30 January 2025

Australian university joins $230m future materials project backed by mining giant

A $230 million project investigating ways to make extracting future materials more sustainable will bring…

30 January 2025

“Like a Corolla with racing tyres:” Why Australia’s outdated electricity market fails renewables

Australia’s electricity market is old, outdated and not doing enough to drive investment in the…

30 January 2025