NSW Planning gives green tick to another wind farm in New England

Published by

Plans to build a 192MW wind farm as part of hybrid renewables and battery hub in the New England region of New South Wales have been referred to the state’s Independent Planning Commission, after being recommended for approval by the state government.

In a letter of referral delivered to the IPC last week, the NSW Department of Planning said it considers Neoen Australia’s Thunderbolt Wind Farm, proposed for construction 47km northeast of Tamworth, “approvable, subject to the recommended conditions of consent.”

Neoen’s Thunderbolt Energy Hub proposes to combine up to 380MW of wind power, over two stages, plus 120MW of solar and a 400MW battery (MWh not yet specified) on land spanning the Tamworth Regional and Uralla Shire.

The state significant project was referred to the IPC after attracting more than 50 public submissions in objection to the development of the stage one, 32-turbine wind farm, including from the Uralla Shire Council.

According to the department of planning, a total of 100 unique submissions were received during the exhibition of wind farm’s Environmental Impact Statement (EIS), as well as advice from 15 government agencies and the two host councils. Of the public submissions, 82 objected to the project, 14 supported it and four provided comments.

The vast majority of the objecting submissions were concerned about potential impacts on the local community – including from turbine noise and visual disturbance – and on biodiversity, as well as potential health impact on livestock. Concerns about the impact of the wind farm on the local economy were also common.

Neoen has since amended the planning application to address some of the concerns raised, including to include a temporary above-ground pipeline for water supply during construction phase – and the amended application has been approved by the department.

The referral letter also notes that Neoen has offered to enter into a community benefit scheme/voluntary planning agreement with the Tamworth and Uralla councils, with contributions of more than $5.6 million towards community enhancement projects.

The Thunderbolt wind farm sits in the New England REZ, which has been identified by the NSW government as as potentially hosting 8,000 MW of renewable energy.

It is also on the doorstep of the federal electorate held by former Nationals leader Barnaby Joyce, who earlier this month headlined at an anti-renewables rally held outside federal Parliament in Canberra.

At the rally, Joyce railed against “reckless renewables”and decried wind turbines as “filth.” Meanwhile, on the same day, the NSW IPC waved through the more than 300MW Bowman’s Creek wind farm near Muswellbrook.

The New England region will also host the Hills of Gold solar farm, which has also received planning department approval but which is also being assessed by the IPC.

Origin Energy has has bought a 7690-hectare sheep and beef property there as a prospective greenfield wind development opportunity, and last week bought two wind and solar projects near the town of Walcha that it also wants to develop.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Advocates unhappy as government seeks oversight of home solar, battery and EVs, rather than regulator

Consumer energy advocates unhappy the federal government will hand technical oversight to its own department…

10 September 2026

Regulator wins fraud conviction against solar installer as Bowen bats off battery rebate rorting claims

Regulator says "enforcement action will be taken where it is warranted," as it secures a…

10 September 2026

Labor dials back gas reservation scheme, denies the move is a policy back-down

The government has tweaked a plan to ease energy prices, with gas producers to only…

10 September 2026

Spanish giant withdraws 2,000 MWh battery project after being “called in” by LNP planning minister

Spanish energy giant withdraws a massive battery project after being "called in" by planning minister,…

10 September 2026

Data centres told to pack their bags for the regions after house full sign goes up in Sydney

Australia's biggest transmission company has effectively put the "house full" sign up for data centres…

10 September 2026

All 200,172 panels in place, as one of Australia’s first solar-battery hybrids hits construction milestone

One of Australia’s first solar and battery hybrid projects has completed the installation of all…

10 September 2026