NSW Planning blocks Crookwell 3 wind farm, in heart of Taylor’s electorate

Published by

The NSW Department of Planning and Environment has opposed the granting of development approval for the Crookwell 3 Wind Farm after receiving submissions raising visual and noise concerns about the project.

In a decisions that involves – directly and indirectly – some of the major protagonists in the debate about siting wind farms, the project will now be considered by the Independent Planning Commission for NSW, but the Department has recommended that the commission refuse development approval.

In recommending the project be rejected, the Department said that it did not think the project was necessary to meet State and Federal targets for renewable energy and emissions reductions, even though the NSW Government does not currently have a target for renewable energy.

The NSW Government released a new NSW Wind Energy Framework in 2016, which placed stricter rules on the positioning of wind turbines and requires planners to take into account the visual impacts of a wind farm.

Local land holder Matthew Donoghue, who would have hosted part of Crookwell Stage 3 and who had worked on the construction of Stage 2, told RenewEconomy that it is ultimately the community that loses out.

“Everyone is a loser here. If you start with the developer, they don’t get to finish the second half of their project, this extends to their suppliers, and the workers in the region that would have worked on the construction of the project. Through to me as a landholder and the wider community and a lost opportunity to further decarbonise the electricity sector,” Donoghue said.

This disappointment was echoed by the Australian Wind Alliance, which was optimistic that the project developers would be able to respond to the setback.

“It is very disappointing to see this project stalled. The fact that the Department recommended this project be approved in 2015 just highlights the difficulties industry has faced navigating the challenges of shifting government priorities.” Australian Wind Alliance national coordinator Andrew Bray told RenewEconomy.

“We look forward to seeing what the proponent can bring forward to resolve the issues the Department has raised.”

The NSW Department of Planning and Environment said that it had assessed the project in inline with community feedback.

“We considered this project on its merits, and our recommendation to refuse it draws on extensive community consultation and advice from an independent visual expert.” Mike Young, Executive Director of Resource Assessments for the Department said.

“There’s strong support for renewable energy in NSW and the Government is backing the industry’s development including with guidance on assessment of impacts, community engagement and more,” he said.

The Crookwell Wind Farm is located in the within the electorate of Federal Energy Minister Angus Taylor, who has been outspoken in opposition to wind farm developments, and did not attend the opening of the Crookwell 2 wind farm earlier this year, despite being the local member and the country’s energy minister.

Minister Taylor’s office said, however, that the minister had not engaged with the planning process. “Planning approval for these projects is a matter for the NSW Government. Taylor did not make a submission,” a spokesperson for Taylor said in an emailed statement.

One nearby resident is vocal wind farm opponent Maurice Newman, the former ABC and ASX chair who while serving on Tony Abbott’s Business Advisory Council called for the Renewable Energy Target to be scrapped. Newman’s wife has served as Chairwoman for the Crookwell District Landscape Guardians.

Stage 3 of the Crookwell Wind Farm would have been an extension of the existing Crookwell developments, with an additional 23 wind turbines.

The first stage of the Crookwell wind farm consists of eight turbines, with an additional 32 wind turbines for Crookwell Stage 2, where the third stage would also have been located.

The NSW Southern and Central Tablelands have excellent wind resource availability and has attracted significant investment in wind generation. There are currently seven operational wind farms in the region, despite long term opposition from Taylor and the former local state member Pru Goward.

In recommending the project be blocked, the NSW Department of Planning and Environment cited opposition from three “special interest groups”, the Parkesbourne-Mummel Landscape Guardians, the Crookwell District Landscape Guardians and NSW Landscape Guardians.

All three of the “Landscape Guardians” have voiced opposition to numerous wind farm developments in the region, and have been linked to other anti-wind farm groups, such as the Waubra Foundation.

The Crookwell region has been a target for anti-wind farm groups, who have raised fears about the visual and noise impacts of the wind farms, often convincing residents who live in the vicinity of a project to voice opposition.

The Department of Planning and Environment received 81 submissions from members of the community in response to the planning request for Crookwell 3. The majority of these submissions voiced support for the wind farm.

However, the department noted that 15 of 18 submissions from residents located within 5km of the wind farm were opposed to the wind farm.

In response to community concerns about the location of the wind turbines, project developer, Global Power Generation Australia amended the plan for Crookwell 3, reducing the number of turbines to be constructed.

“We acknowledge the proponent has made changes to reduce impacts and has reached agreement with a number of landowners, but our independent visual expert has advised there would still be significant visual impacts on up to 27 residences.” Young said.

The National Wind Farm Commissioner confirmed that it had not been directly engaged in the planning process, nor had it received any formal complaints about the Crookwell 3 development.

If approved, Crookwell Stage 3 would see the construction of 96MW of wind generation capacity, generating $120 million of investment in the region and the creation of 40 jobs during the construction phase.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Share
Published by

Recent Posts

Northern Hemisphere extreme heat records just a warm up for the full El Niño theatre

We've seen impacts of the record-breaking El Niño in the Northern Hemisphere – including heat-related…

12 August 2026

The NSW koalas-for-coal shakedown – and what it reveals about the carbon offset market

The NSW government's plan for a Great Koala National Park now includes seeking the rights…

12 August 2026

NSW won’t rule out slippages to coal closure timetable, as first turbine deliveries highlight lack of new projects

NSW energy minister says government will make "hard decisions to extend" coal closures where required,…

12 August 2026

Why solar didn’t work for this dairy farmer, until he added a battery and put it on wheels

High hot water use, an unreliable grid, and milking in the dark were all challenges…

12 August 2026

Coal will close to schedule, says AGL, but to build more wind we need policy certainty in return

AGL says it will stick to its dates for coal plant closure, but wants policy…

12 August 2026

“No silver bullet:” Wind farms need site-specific technology to avoid bird and bat turbine collisions

No one system prevents bird and bat turbine collisions, but a mix of strategies from…

12 August 2026