NSW greenlights network link to unlock wind and solar in state’s south-west

Published by

The NSW government has given the green light for a major part of the $1.8 billion transmission network link between New South Wales and South Australia that will underpin a ramp-up of investment in new wind, solar and storage projects.

On Thursday, NSW planning minister Rob Stokes said the government had given planning approval for the first stage of Project EnergyConnect, a new 900-km transmission line linking Wagga Wagga to Robertstown in South Australia, with an additional ‘spur’ link into Victoria.

“Today’s approval is a major step towards facilitating the delivery of what would be the largest energy transmission project undertaken in Australia in more than 30 years,” Stokes said.

“The first stage will run from the Buronga substation to the Victorian border and create 600 construction jobs and inject $418 million into our regional economy.”

“To get to a low-emissions energy system our nation needs robust and reliable transmission infrastructure and that’s why we declared Energy Connect Critical State Significant Infrastructure in 2019 because it will be a fundamental part of Australia’s energy future,” Stokes added.

The EnergyConnect project will significantly expanding the amount of electricity that can be shared between the two states, as well as increasing network capacity across south west New South Wales, which has been limited and has caused constraints on wind and solar farms.

The first stage of the project will now be referred to the federal government for further environmental approvals, with construction expected to begin sometime next year.

NSW energy minister Matt Kean said the project would help unlock investment in new wind and solar projects, supporting the development of the South-West Renewable Energy Zone.

“The Electricity Infrastructure Roadmap is our plan to replace our ageing electricity infrastructure and secure NSW’s future as a clean energy superpower,” Kean said.

“This approval will help to unlock transmission constraints in southern NSW and help to open up the South-West Renewable Energy Zone (which) will drive jobs and investment into regional NSW, and help to provide our households and businesses with some of the cheapest, cleanest electricity anywhere in the world.”

The NSW side of the EnergyConnect project is being constructed by Transgrid, with ElectraNet to take responsibility for the South Australian component.

Acting Transgrid CEO Brian Salter said the project would eventually generate savings for New South Wales energy consumers of up to $180 million a year in combined energy costs and support a further $4 billion in economic activity.

“The project will be the critical missing link in the NEM, connecting more renewable generation and reinforcing connectivity between the state grids of NSW, South Australia and Victoria,” Salter said.

Environmental approvals for the western section of the EnergyConnect project follows Transgrid securing backing from the federal government to bring forward upgrades to an ‘eastern’ portion of the EnergyConnect project.

Announced on Tuesday, Transgrid will spend $180 million upgrading the network link between Wagga and Spark Infrastructure’s proposed Dinawan renewable energy hub.

This upgrade will form part of the EnergyConnect link and avoid upgrading the same part of the network when the VNI West interconnector is built between New South Wales and Victoria.

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.
Michael Mazengarb

Michael Mazengarb is a climate and energy policy analyst with more than 15 years of professional experience, including as a contributor to Renew Economy. He writes at Tempests and Terawatts.

Recent Posts

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026

Massive wind project, with up to 280 of Australia’s biggest-ever turbines, seeks federal green tick

Plans for a potentially massive new wind farm start federal environmental assessment, proposing up to…

7 August 2026