NSW formally opens big battery tender as questions loom over Eraring closure

Published by

The competitive tender for 380MW of “firming infrastructure – likely to be a big battery – has been formally opened in NSW despite lingering questions over the future of the country’s biggest coal generator, the 2.8GW facility at Eraring.

The new facility – widely expected to be a two-hour battery – is being sought as part of the planned replacement of the Eraring capacity, along with a series of tenders for new wind, solar and long duration storage, and the planned Waratah “super battery.”

However, the newly elected Labor minority government in NSW has raised questions about the future of Eraring, saying it was not happy it was due to close so early (August, 2025), and raising the possibility it may buy the asset to keep it running longer.

Market analysts have suggested that a short term extension of at least one or two of Eraring’s 720MW units may be needed to cover supply needs over the summer of 2025/26.

But the potential purchase of the facility by the state government is a different ball game, and raises many big questions about the transition to renewables in what is the country’s biggest state grid, and with the biggest and oldest fleet of coal generators.

The tender for the 380MW of firming infrastructure is being managed by AEMO Services.

Unlike the long duration storage sought elsewhere in the state, this will be focused on at least two hours storage to help manage any short term shortfalls, and it must be located within the major demand centres of Sydney, Newcastle or Wollongong.

AEMO Services general manager Paul Verschuer says the tender is needed because of the earlier than previously scheduled closure of the Eraring Power Station. 

“Firming infrastructure is a critical component of any reliable power system and will be needed when intermittent generation resources, like wind and solar, are not available,” he said in a statement.

The tender is open to a range of technologies, including batteries, pumped hydro gas and biofuels, and demand response. But because of the speed and flexibility of battery storage, it is likely that a battery project will win the tender, market participants say.

However, it is also the first time that demand response will compete directly with other new infrastructure assets in a competitive tender. So, if enough demand can be sourced, from a refinery or aggregated from other users, that may present an interesting choice for tender managers.

“Demand response is an innovative, cost-effective solution already being used widely around the world,” Verschuer said.

“It encourages businesses to reduce their consumption during periods of high demand and get paid to do this. This helps free up supply to the market, while reducing the overall need to build new infrastructure, which ultimately drives down costs for consumers.

Proponents have until May 18, 2023 at 5pm to finalise their submission.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024