Still no word on Snowy 2.0 as Bowen underlines importance of transmission: “They are not being built for fun”

Published by

Transmission projects worth billions of dollars were “not being built for fun”, and were vital for modernising a grid requiring strengthening to cope with an expansion of renewables supply and rising power demand, Federal Climate Change and Energy Minister, Chris Bowen, said.

Addressing a vow by the Victorian Opposition last week that it would scrap the VNI-West project if it won office in November, Bowen told Renew Economy on Friday his government was “monitoring” the situation and how any changes might affect the grid.

“In the broad [view], new transmission is necessary not just to bring renewables on, just because of the … increase in electricity use across the country,” he said.

“The energy grid had been underinvested in for 50 years, in terms of transmission,” Bowen said. “We’re fixing that.”

He cited progress on the Hume Link, intended to connect the giant Snowy 2 pumped hydro project to the rest of the grid. Project Energy Connect linking NSW and South Australia, meanwhile, was “basically finished”.

“VNI West is important for Victoria and for the [National Electricity Market],” Bowen said, adding “obviously … we’ll await the results for the Victorian election, and we will deal with the situation after that.”

The NSW Opposition has similarly pledged to cancel a major transmission line and downgrade the country’s biggest renewable energy zone, in New England, should it win office in that state’s elections next March.

While polls rate such a change of government as less likely in NSW than Victoria, Bowen took a similar stance on any policy that would rip up existing plans.

“The transmission lines aren’t being built for fun,” he said, adding the enabling of more renewables to join the grid only part of the reason to proceed. “Obviously, renewables will fill the wires, but … we need new transmission regardless.”

This week’s release of the Electricity Statement of Opportunities (ESOO) by the Australian Energy Market Operator underscored the need for the contruction of new generation, storage and transmission to maintain grid reliability.

The report listed August 2029 as the operational start date for stage one of VNI-West, with November 2031 listed as the switch-on date for stage two. VNI-West is slated to increase the electricity transfer between Victoria to NSW of 1885 megawatts, and 1669MW between NSW and Victoria.

AEMO’s ESOO report also listed the New England Renewable Energy Zone Infrastructure Project, with its increase in network capacity of 6 gigawatts, as commencing from January 2034.

One of the tunnel-boring machines operating at Snowy 2. Source Snowy Hydro.

Separately, Bowen said he is yet to receive a delayed cost review of the Snowy scheme.

As Renew Economy’s Giles Parkinson reported earlier this month, the line-by-line review was announced last October by the federal government-owned Snowy Hydro when it flagged yet more cost overruns and potential delays.

“The situation remains, as I previously indicated,” the minister said on Friday. “It’ll be released after I’ve received it.”

Renew Economy contacted Snowy Hydro for comment.

AEMO’s ESOO report lists Snowy 2, with its 2.2GW/350GW-hours of capacity as commencing in December 2028, or about 28 months from now.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Peter Hannam is a veteran journalist whose work spans almost four decades and includes stints outside Australia, including time in China, Japan, Singapore and Mongolia. He has lately reported extensively on energy, climate and environmental issues in Australia, and also worked for the federal Climate Change Authority as a special media advisor.

Peter Hannam

Peter Hannam is a veteran journalist whose work spans almost four decades and includes stints outside Australia, including time in China, Japan, Singapore and Mongolia. He has lately reported extensively on energy, climate and environmental issues in Australia, and also worked for the federal Climate Change Authority as a special media advisor.

Share
Published by

Recent Posts

Cows and cyclones: New push to design solar farms for cattle and climate, but is Australia ready?

Companies are looking again at how to put more farmland under solar without disrupting operations…

5 November 2026

Data centre probe prompts call for tighter renewable energy requirements in coal state

A NSW parliamentary inquiry has recommended the government require data centres to supply their own…

5 November 2026

Low-cost green hydrogen hopeful lands fresh grant to build pilot at site of proposed offshore wind hub

Green hydrogen CSIRO spin-off wins new grant funding to build fourth pilot plant, this time…

5 November 2026

The rise and fall of the LGC market and the data centre policy decision that will determine its fate

A seemingly niche decision around data centre standards will determine whether LGC prices retain some…

5 November 2026

Huge wind and battery project avoids turbine cuts and name change to win state approval for the West

Developer dodges having to cut 18 turbines from its 750 MW wind plans and change…

5 November 2026

State tightens reins on home energy saver loans after signing up 15,000 households in just 5 months

Energy efficiency is so hot right now. After signing up more than 15,000 households to…

5 November 2026