Coal

Nice work if you can get it: $65,800 a megawatt hour to keep the lights on

Published by

More details have been released about the reserve trader mechanism deployed in Australia’s most coal dependent states over the last few weeks – and it seems that the last activation has been the most lucrative.

According to the Australian Energy Market Operator, its Reliability and Emergency Reserve Trader (RERT) mechanism was activated in Queensland on July 5 in response to a “lack of reserve 2” declaration, meaning that just one more outage could have triggered load shedding for some consumers.

It appears that not much of the RERT capacity was needed, and in the end just 10 megawatt hours (MWh) was deployed, but at an eye watering cost of $658,211, or an average of $65,821/MWh.

That sum does include “pre-activation” costs, but industry insiders say this is usually not significant. There was no immediate information on what sort of technology or industry was deployed at that cost.

It could, for instance, have been a large smelter that reduced consumption, or “aggregated” offerings from commercial and business consumers. We have asked AEMO if more information will be revealed.

While the per megawatt hour cost of the latest activation was extraordinary high, the sort of rate former prime ministers and presidents charge for after-dinner speeches, the total cost of that event is just a fraction of previous activations.

For instance, more than $86 million was spent on RERT activations in May and June, when the RERT was deployed on multiple occasions in response to the energy crisis and ongoing coal plant outages, particularly in NSW which struggled to meet capacity.

As we reported in late June – see The staggering cost of Australia’s fossil fuel energy crisis – those multiple RERT activation were delivered at an average cost of more than $20,000/MWh, and all but $4 million of it to providers in NSW.

It included payments of $29.9 million paid to providers in NSW on June 17 and 18, $34.3 million to NSW and Queensland providers on June 15, and $21.6 million to NSW providers on June 14.

Of course, as we also reported, this pales in significance to the total costs of the energy crisis.

Compensation payments under the price cap that was automatically triggered when the soaring cost of coal and gas generation pushed wholesale market prices into the stratosphere, and the later market suspension forced by the withdrawal of capacity, will total well over $1 billion, and up to $1.6 billion.

And the total cost of the soaring prices has translated into a more than doubling of market turnover on the National Electricity Market to more than $26 billion in 2021/22, up from $11.9 billion in the previous financial year.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024