New four-hour big battery seeks green tick for Queensland coal country

Published by

A new four-hour big battery proposed for Queensland coal country has joined the queue for assessment by the federal government, under the Environmental Protection and Biodiversity Conservation (EPBC) Act.

The up to 440 megawatts (MW) and 1760 megawatt-hour (MWh) battery energy storage system (BESS) is being proposed for development by Acen Australia in Lilyvale in Queensland’s Central Highlands region, 52 km north-east of Emerald.

EPBC referral documents say the Lilyvale BESS proposes to install 512 battery containers, 128 inverters and 128 medium voltage power stations and associated electrical and control equipment in a project area spanning roughly 151 hectares.

Within that area, Acen says the disturbance footprint of the BESS will be around 21 hectares and located entirely on land with non-remnant vegetation and that has been historically cleared or altered for agricultural practices. There are also existing mineral extraction licenses and granted mining leases over the project area.

“The surrounding area is dominated by existing coal mine operations to both the north and south,” the documents say, nothing the project area is located 3.4 km northeast of the Bowen Basin coalfields and Gregory/Crinum Mine and just 1 km south of multiple coal mine sites, including Mancala Oaky Creek North, Oaky Creek North and Aquila.

The referral also notes that the battery would connect to the existing Lilyvale substation operated by Powerlink, which is located around 1.5 km south of the proposed project.

To the north of the proposed Acen BESS is FRV Australia’s 100 MW Lilyvale Solar Farm, which first powered up in 2019.

A few kilometres north-west of the Acen project, a 400 MW 2,000 MWh BESS is being proposed by Atmos Renewables, with a development application submitted to the state government a couple of months ago, according to RenewMap.

RenewMap also displays a 215 MW PV project by Renewable Energy Developments called the Gregory Solar Farm, which is recorded as having secured EPBC approval for construction adjacent to the Lilyvale BESS, but its development application has been withdrawn.

See also Renew Economy’s Big Battery Storage Map of Australia for more information.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Solar Sharer free power offer is being undermined by higher network charges and complex tariffs

Some households will use batteries, EV charging and behaviour change to make very good use…

3 July 2026

China battery giant launches major new push for “circularity” amid EV and home storage boom

China battery giant launches two major initiatives aimed at improving the sustainability of battery manufacturing,…

3 July 2026

Government-backed community battery rollout is way behind schedule, with only a quarter built on time

A report into the progress of the federal government's Arena-backed community battery rollout has revealed…

3 July 2026

One of Australia’s first solar and battery hybrid projects reaches financial close, confirming big shift in market

One of Australia's first solar and battery hybrid projects reaches financial close, confirming big shift…

3 July 2026

Solar battery rebate expanded to apartments and big energy users for up to 30 MWh in game-changing move

State government quietly reboots its paused solar battery rebate and expands the scheme to offer…

3 July 2026

Australian software allows Italian homes to get free power from solar panels in Spain. Why not here?

Innovative energy trading using Australian software is "going gangbusters" in Europe – and making our…

3 July 2026