Mount Emerald Wind Farm reaches major construction milestone

Published by

PRESS RELEASE

Construction at the $360 million Mount Emerald Wind Farm near Mareeba reached an important milestone last week when the first of 53 turbine foundations was put in place.

The 800-tonne foundation which is buried to ground level provides an immovable anchor for each turbine and consists of a 50-tonne reinforced steel cage filled with around 350m3 tonnes of concrete, or up to 70 truckloads.

Ratch Australia Corporation Executive General Manager Business Development, Mr Anthony Yeates, said the first foundation was always a special milestone in wind farm construction.

“Up until this point, the focal point for construction has been civil works, establishing the site office and constructing access roads following meticulous flora, fauna and unexploded ordinance surveys,” Mr Yeates said.

“Getting the first foundation poured is the first big ticket items on our scope of works that has to do directly with the wind turbines so for us it’s a special moment that salutes years of hard work by many people in our team,” he said.

Mr Yeates said the concrete used for each foundation will be manufactured onsite to reduce truck movements on public roads. Up to four weeks is allowed for the concrete to cure to maximum strength before the foundation is backfilled with rock and soil to match the natural surface level.

At this point, the foundation is ready for the bottom section of the tower to be bolted to it.

Wind turbine components will be delivered over an eight-month period starting in October. The delivery route will see trucks head south from Cairns along the Palmerston and Kennedy Highways before Hansen and Springmount Roads are used to get to site.

All parts will be delivered with the approval from the Department of Transport and Main Roads for oversize loads.  A detailed route assessment plan including any proposed modifications to intersections is required for this approval.

Each turbine will have a capacity exceeding 3 megawatts (MW) making a total capacity of around 180MW to be connected to the electricity grid. Once fully operational in September 2018, Mount Emerald will be the biggest wind farm in Queensland.

“It’s exciting to see the project really begin to take shape. Now that we have the foundations underway, we hope to have the first tower sections going up within the next two months, followed eventually by the installation of the nacelles and then the turbine blades,” Mr Yeates said.

Share
Published by

Recent Posts

Renewables sector learning from messy failures after oil company collapses with $200m clean up bill

Another oil and gas company collapse raises new concerns about who picks up massive clean…

15 July 2026

Data centres will have “legal obligation” to BYO renewables, says PM, but LNP looms as spoiler

PM says data centres will have a "legal obligation" to meet their own energy needs…

15 July 2026

SwitchedOn podcast: Why the booming home battery market is staying clear of virtual power plants

Despite the potential for lower bills, and a stronger grid, most battery owners still aren't…

15 July 2026

Flood-prone rugby fields, gaps in regional health: First round of REZ grants back 46 community projects

New drainage systems for flood-prone sports ground and a new community health hub are among…

15 July 2026

Coal closure plan urgently needed as unreliable clunkers push power prices through roof

The growing unreliability of end of life coal fired power plants is costing Australians and…

15 July 2026

Rinehart-backed miner signs deal to make magnets for wind turbines and EVs

A Rinehart-backed miner has signed a deal to partly fund and supply rare earths for…

15 July 2026