More contractors stung by connection delays for renewable energy projects

Published by

More contractors have been stung by the costs of connection delays for renewable energy projects, with the listed developer Infigen Energy disclosing that it received more than $10 million of “compensated revenue” from delays at the Bodangora wind farm in NSW.

Details of the issue are scant, and Infigen has declined to comment further. It said in a brief statement accompanying its latest production and revenue figures that it had received $10.1 million of compensated revenue.

It said this was “primarily relating to liquidated damages for construction delays at Bodangora Wind Farm.”

The 113.2MW Bodangora facility started production a year ago, after work on the site began in June, 2017. The EPC contractors were named in Infigen press releases at the time as Civil and Allied Technical Construction Pty Ltd (CATCON) and General Electric International Inc. (GE) which manufactured and supplied the turbines.

The overhead powerlines connecting the wind farm to the electricity grid have been built by TransGrid.

Bodangora is just the latest in a long and growing line of wind and solar farms that have experienced delays in connection and commissioning, and which have resulted in “compensated revenue”, or “liquidated damages” and which in some cases has taken a heavy toll on contractors.

RCR Tomlinson collapsed under the weight of cost over-runs, damages claims and cash flow delays as the result of problems at nearly one dozen solar farms it was working on, while Downer Group, Bouyges, Tempo Australia and others have also been hit by damages claims or cost over-runs.

In Queensland, Adani Renewables’ Rugby Run solar farm was only connected more than six months after the solar farm’s machinery was in place, and an even longer delay affected the world-leading wind-solar-battery complex at Windlab’s Kennedy Energy Hub.

The problems have been variously blamed on the sheer number of projects seeking to connect at the same time, tight new connection rules, last minute alterations, the lack of preparedness by some developers and contractors, and the lack of resources in network companies.

Some contractors, such as Tempo, have sought to renegotiate contracts, avoiding the threat of liquidate damages, while there is a growing debate about who should take responsibility for connection delays, the developer or the contractor.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

“Remarkable milestone:” Bowen says home battery installations continue to surge, pass 400,000

Home battery installs continue to surge despite rebate changes, passing 400,000, and matching the storage…

16 May 2026

Coal pollution is significantly reducing the output of solar panels, major study finds

Study by University of Oxford and University College London finds that coal pollution is significantly…

16 May 2026

Turbine blade breaks, falls to ground at wind farm damaged by lightning strike in 2019

A wind turbine blade has broken and fallen to the ground at a wind farm…

15 May 2026

Construction starts at state’s first “end-to-end” hydrogen and ammonia production plant

Construction is underway at state's first hydrogen and ammonia production plant, that will help insulate…

15 May 2026

Angus Taylor’s energy policy is now a carbon copy of Hanson and Trump

It is now almost impossible to spot the difference between One Nation's policy on climate…

15 May 2026

Utility giant bets big on data centre demand with plans to build Australia’s biggest gas plant

EnergyAustralia plans to build the nation's biggest ever gas plant to help fill a supply…

15 May 2026