Governments

Market operator still not told of Snowy 2.0 delays, but it won’t be missed much

Published by

The Australian Energy Market Operator has still not been told by the government-owned Snowy Hydro that its signature Snowy 2.0 pumped hydro project is delayed. But the market operator says that if the multi-billion project is not ready on time, it won’t be missed much.

The situation around Snowy 2.0 is really quite extraordinary. The principal contractor, Clough, revealed in late June that the project is 18 months behind schedule, at least partly because it struggled to find people trained to use the giant boring machines needed to tunnel into the mountain side.

Clough insisted in a presentation to analysts that Snowy had communicated the delays to the market, but it’s actually done nothing of the sort. It certainly hasn’t told the market operator, who – you might think – would like to know.

We now have the bizarre situation where the company’s contractor says the project is delayed, and the company’s owner, through energy minister Chris Bowen, also says the project is delayed. But as recently as July, when AEMO did its latest call for updates, Snowy Hydro insisted the project was running on time.

It is possible this might have had something to do with the dispute between Bowen and Snowy CEO Paul Broad that led to Broad’s sudden resignation last Friday, although Broad chose to focus on disagreements over the Kurri Kurri gas/hydrogen generator in his subsequent radio interviews.

Someone in AEMO, however, is reading the media, and the market operator has prepared a special scenario as part of its 10-year supply outlook known as the Electricity Statement of Opportunities (ESOO) to consider what would be the impact if Snowy 2.0 did turn out to be delayed by 18 months or two years.

Remarkably, it turns out that Snowy 2.0 won’t be missed much.

The first reason for this is that it is quite possible that HumeLink, one of the main transmission projects designed to connect Snowy 2.0’s storage to the rest of the grid, won’t be ready in time.

And, according to AEMO, even if HumeLink is ready, other generators will be able to use that link to deliver their output to the major load centres.

It does beg the question: Do we really need Snowy 2.0? Perhaps, in the long term, its claimed storage of 350GWh will be useful for seasonal fluctuations and what the Germans call “Dunkelflaute”, although there is some question about how much of that storage capacity will actually be available, given restrictions on river flows, etc.

AEMO says that despite the media speculation about the delays (and the quite explicit observations of the company’s owner and major contractor, Snowy Hydro has provided “unchanged advice regarding the intended commissioning schedule of Snowy 2.0 between 2025-26 and 2026-27 since the 2021 ESOO.”

But, just in case, and in light of the media reports, it modelled a potential delay that would put its commissioning back two years to 2027-28 and 2028-29.

According to AEMO: “Without the development of HumeLink, the project is not able to deliver a reliability benefit in the ESOO Central scenario, and likewise does not reduce reliability if it were delayed in this case.”

But then it adds:

“A delay in Snowy 2.0 would have a small impact on forecast reliability, with an increase in New South Wales USE (unserved energy) in 2026-27 and 2027-28.

“Without Snowy 2.0, the HumeLink and Hunter Transmission projects allow extra generation to flow into the major New South Wales load centres of Sydney, Newcastle and Wollongong, from other generators in southern New South Wales, Victoria and/or South Australia prior to Snowy 2.0 commissioning.”

That’s an assessment that might reinforce many people’s views that Snowy 2.0 is crowding out other projects, and might be more important for its own business model and position in the market, than it is for the energy transition as a whole.

See also: Crunch time for grid: More wind, solar, storage and links urgently needed before coal exodus

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

“A thin veneer of governance:” Senate inquiry identifies critical failings in energy transition

Weaknesses in governance, planning and economic efficiency in the NEM are historic, but completely inadequate…

11 February 2025

Explainer: What does it actually mean to “firm” renewables?

How does renewable energy firming work, how are we tracking with it in Australia and…

11 February 2025

Regulator rejects gas network bid to hike costs, says customer exodus will be slower than forecast

A bid to charge Victorian gas customers an extra $70m to cover the cost of…

11 February 2025

Will it or won’t it? South Australia hedges bets on world-leading green hydrogen plan

South Australia premier refuses to commit funds for what would be a world-leading green hydrogen…

11 February 2025

Sharp quits solar business in Europe, citing “challenging conditions”

Citing “challenging conditions" in the European market, Sharp pulls the pin on its German-based solar…

11 February 2025

Brown coal hits new low in Victoria as wind and battery records tumble and renewables peak at 95.2 pct

Records fall in Victoria, with brown coal and demand hitting new lows, battery output and…

11 February 2025