Policy & Planning

Marinus Link construction heads “into full swing” as regulator delivers final verdict on cost

Published by

The cost to consumers of building the first stage of Marinus Link, an undersea cable connecting Tasmania to the mainland electricity grid, has been approved at $3.4 billion, $27.8 million less than the most recent amount pitched by the huge project’s developers.

The Australian Energy Regulator (AER) on Friday announced its final decision to approve proposed capital expenditure of $3,470.6 million for Marinus Link’s Stage 1, for the construction of a 750 megawatt cable across the Bass Strait

For the associated on-land transmission upgrades in north west Tasmania, the AER has approved proposed capital expenditure of $921.3 million, a $49.8 million reduction on the amount proposed by TasNetworks.

The cost of the massive project has been a major point of contention – it was first proposed as two cables with a combined capacity of 1500 megawatts (MW), but was cut in half in late 2023, in response to ballooning costs.

Marinus Link Pty Ltd (MLPL) and Tas Networks had, in July, put costs for the pared back project at $3.89 billion for the cable and $1.14 billion for the supporting North West Transmission Developments (NWTD), but later revised this number down by around $40 million.

In early August, Final Investment Decisions (FID) were announced by the Tasmania, Victoria and federal Labor governments, which hold 17.7 per cent, 33.3 per cent and 49 per cent shares in MLPL, respectively.

In early September, Marinus Link reached financial close on Stage 1 of the project off the back of a record commitment from the federal government’s green bank of up to $3.8 billion in concessional finance.

The AER says its final decision on the public spend for Marinus Stage 1 construction costs included a “reduced, efficient risk allowance” and reduced corporate costs.

“This adopts a balanced approach to risk sharing between Marinus Link and consumers, providing incentives for Marinus Link to mitigate risks and contain costs that are ultimately paid for by consumers, while providing it with the opportunity to recover its construction costs,” the decision says.

MLPL said in a statement on Friday that the regulator’s assessment recognises the discipline shown in managing the project’s construction costs on behalf of electricity consumers.

“Our role now, as a regulated company and the custodians of national energy infrastructure, is to deliver efficiently, responsibly, and ensure the benefits are enduring for all Tasmanians and Victorians,” said MLPL chief Stephanie McGregor.

“Preparatory works are already underway across our project footprint. This final decision gives us the confidence to take construction into full swing later this year.”

Costs for Marinus Link will be recovered from Tasmanian and Victorian electricity consumers once the interconnector comes into operation, with a target date of around 2030. The allocation of costs will be based on an agreement between governments.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.




Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Marinus Link

Recent Posts

Vestas lands turbine order for landmark wind and green hydrogen refuelling network in New Zealand

A landmark renewable energy and green hydrogen project in New Zealand has reached financial close…

9 February 2026

Plan to increase fixed network costs will take from the poor, give to the rich and slash returns on PV and batteries

Households could face a four-fold increase in network costs as a result of the regulator's…

9 February 2026

“Don’t reinvent the wheel”: Big investors fear NEM reform could backfire on wind industry

A major reform intended to drive investment in renewable energy and storage capacity could have…

9 February 2026

HMC ready to invest in first big battery project after landing major cash deal with investment giant KKR

HMC is expected to move on its first new big battery project, after securing a…

9 February 2026

Another two big battery projects fast-tracked through state planning process

State government fast-tracks approval for another two battery storage projects, taking total number of projects…

9 February 2026

Danish giant lodges EPBC referral for first of its two Gippsland offshore wind projects

Federal green tick sought for 2.8 GW offshore wind project, but final scale will depend…

9 February 2026