Lord Howe Island to get solar and battery microgrid, no wind turbines

Published by

Lord Howe Island’s long and rather fraught journey to a renewable power supply is back on track, with a new funding package from the Australian Renewable Energy Agency – this time for solar and storage without the wind turbines.

The remote New South Wales island will install a minimum 1.2MW of solar and a 3.2MWh battery system, according to a statement from ARENA on Thursday, with the help of $4.5 million in funding from the federal government agency, and a loan facility of $5.9 million from the NSW government.

ARENA said the project’s development was set to commence “soon,” with Photon Energy Engineering Australia awarded the tender by the (much relieved) Lord Howe Island Board.

The ARENA funding for the $11.1 million project comes more than five years after a first offer of $4.5 million was extended by the Agency, back in July of 2014 – at that time for a combination of 450kW of solar, 550kW of wind (two turbines), and battery storage.

But the LHIB’s efforts to wean the Tasman Sea island from its costly and polluting diesel fuel power supply hit a wall in 2017, when then energy minister Josh Frydneberg intervened to rule out the two wind turbines.

The intervention sent the project – which was at that point seeking tenders to design and build the microgrid – back to the drawing board, and forced the withdrawal of the ARENA grant, which was specifically for a solar, wind and battery microgrid.

Frydenberg had argued that the two wind turbines would have an “unnacceptable” impact on the Island’s World and National Heritage values, and particularly on its ‘visual landscape’.

But the decision was controversial in light of the anti-wind stance the federal Coalition had increasingly been taking – and looked even more so when a recent Guardian Freedom of Information request revealed Frydenberg had overruled his own department in making the call.

Frydenberg’s intervention also flew in the face of economics, at the time. A study conducted by consulting group Jacobs had found that a combination of solar, battery and wind was going to achieve a 70 per cent reduction in the island’s diesel generation, while a solar and battery only system would cut diesel by just 35 per cent.

In its statement this week, however, ARENA said that “further feasibility studies” had identified that a solar PV and battery storage microgrid would provide roughly the same benefits – or more than two-thirds of the island’s electricity supply.

To read the full story on RenewEconomy’s sister site, One Step Off The Grid, click here…

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

Why an oil crisis is bad news for Australia’s biggest coal state – and how to break the cycle

One state in Australia remains particularly vulnerable to global oil shocks because it hasn't built…

13 March 2026

Energy Insiders Podcast: How the world’s fourth biggest economy plans to reach 100 pct clean energy

David Hochschild, the head of the California Energy Commission, on how the world's fourth biggest…

13 March 2026

When will the energy sector understand the National Energy Objective? When will governments enforce its intent?

Fifty years of cheap gas and electricity and intensive marketing have distorted perceptions. Every element…

13 March 2026

“It is paramount:” AEMO says system and market operator functions must be kept together

Australian Energy Market Operator says its system and market operation functions should not be separated…

13 March 2026

Powerful new rooftop solar panel promises system sizes “previously out of reach”

The Clean Energy Council has approved a new PV module with around 25 per cent…

13 March 2026

Webinar: The new era of home energy storage in Australia

An in-depth webinar exploring the next phase of residential battery storage in Australia, brought to…

13 March 2026