Lord Howe Island to install solar, wind and storage to cut back diesel

Published by

One Step Off The Grid

Lord Howe Island has finally called for tenders for the installation of solar, wind and battery storage to meet its long-held goal to reduce its reliance on expensive and dirty diesel generation by two thirds and focus mostly on renewables.

The tender for 450kW of solar PV, 400kW of wind energy and a 400kw/400kWh battery storage system was formally posted by consulting group Jacobs, which has been advising the Lord Howe Island Board, and its financial supporters, the NSW government and the Australian Renewable Energy Agency.

Lord Howe Island expects the new system will cut back diesel use by 66 per cent, from 518,000 litres per year to around 180,000 litres per year. It will also mean that renewable energy accounts or 67 per cent of its electricity needs, ahead of the targeted 63 per cent set out in its energy roadmap put together in 2012.

The Jacobs study canvassed two options, the mix of wind and solar, and solar only (550kW0, but decided that the solar plus wind option presented better value and more diesel reduction. The island also has around 120kW of privately owned solar PV, and has three 300kw diesel generators, although only two are used at any one time.

According to the Jacobs technical report, this is what the energy mix may look like once the renewable energy and battery storage is installed.

 

The whole project, including the scoping study, has been supported by a $4.5 million grant from ARENA and a $5.6 million loan from NSW Treasury, which will be repaid from the savings of reduced diesel use.

“Lord Howe Island is 600km off the east coast of Australia and, like other remote off-grid communities across the country, is heavily reliant on diesel generators that are costly to run and subject to volatile fuel prices,” ARENA CEO Ivor Frischknecht said in 2014, when the funding was announced.

Frischknecht said at the time that the project would transform the energy generation profile of the World Heritage site, which is home to a permanent island community as well as being an iconic Australian tourist destination.

The value of the installation and control systems is estimated at between $3 million and $5 million. Tenders close on August 10. The project is expected to be completed in 2017.

This article was originally published on RE sister site One Step Off The Grid. Click here to sign up for the weekly newsletter.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024