Utilities

Longest running solar farm contract dispute finally settled after more than two years

Published by

The longest running (publicly revealed) contract dispute over the construction of a large scale solar farm in Australia has finally been settled after more than two years of stand-offs, counterclaims and arbitration.

The dispute over the 200MW Sunraysia solar farm in NSW – between lead contractor Decmil and owners John Laing and Maoneng – first came to light in early 2020 and centred over the registration and commissioning delays that plagued dozens of large scale wind and solar projects at the time.

The Sunraysia dispute came to prominence because as listed company, Decmil had to update its shareholders, and like many others at the time, it was about who was to bear the burden of any cost over-runs and lost revenues because of commissioning delays.

The nature of these disputes, deepened by frustrations over the connection and commissioning issues, led to many contractors either collapsing (in the case of RCR Tomlinson) or leaving the industry.

The Sunraysia dispute concerned claims for extensions of time, variations, payment of liquidated damages, return and reinstatement of security and claims concerning alleged defects, according to a Decmil presentation.

Decmil claimed the deduction of liquidated damages, recourse to security and set-off was wrongful. It wrote off $9.7 million in early 2020, and later revealed it was facing a claim of up to $28.7 million in liquidated damages from the solar farm owners.

“Decmil is pleased to announce that it has finalised its dispute with Sunraysia Solar Project trust in relation to the Head Contract of the Sunraysia Solar Farm project in New South Wales,” it said in a statement this week.

“The terms of the settlement are confidential, but Decmil can confirm that the settlement amount to be received is in line with its accounts.”

Another dispute, between Decmil and inverter supplier Schneider, was finalised last October, and it means the matter is now behind them.

The experience caused Decmil to limit its focus to “balance of plant” contracts for large scale renewable contracts, rather than full EPC or head contracts. It was just one of a number of big contractors to exit that part of the market.

“This settlement puts to bed a challenging chapter for Decmil and reaffirms the ability of our strengthened executive team to successfully and methodically deal with our legacy issues,” Decmil CEO Rod Heale said in the company’s statement.

He also noted that the Sunraysia solar farm is currently performing at, or above, its performance obligations “demonstrating the high-quality nature of our work.”

For Maoneng, it also brings an end to a series of problems around its operating assets. The small Mugga Lane solar farm in the ACT was put in administration last year because of a dispute around debt arrangements, and has since been sold to CleanPeak Energy.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024