Renewables

Lincoln Gap wind farm near Port Augusta to add battery storage

Published by
An artist’s rendition of the Lincoln Gap wind farm.

The 212MW Lincoln Gap wind project near Port Augusta is to be the third wind farm in South Australia to add battery storage to its operations, with news that it will build an “unsubsidised” 10MW/10MWh fast response battery array.

The announcement came as project developers, the Singapore-based Nexif Energy announced they had secured $150 million in debt finance from the Clean Energy Finance Corporation, paving the way for construction of the first stage of the project, 126MW, to begin later this month.

The second stage is likely to come with additional battery storage, probably another 20MW/20MWh, although the size and configuration – and whether it focuses on FCAS, or time shifting, or both, will depend on the results of the first stage.

Both companies are hailing the addition of battery storage as signs that the “next” phase of the clean energy transition is well under way.

It follows the Tesla big battery (100MW/129MWh), next to the 315MW Hornsdale wind farm, and the 30MW/8MWh battery to be put next to the 96MW Wattle Point wind farm. (See our round-up here).

Lincoln Gap also highlights the massive change occurring at the old industrial centre at the top of the Spencer Gulf.

Port Augusta, which has seen its two coal generator close in recent years, it is also witness to a 220MW Bungala solar project under construction, and a 1.1GW proposal for wind, solar and battery storage at DP Energy’s Port Augusta Renewable Park.

And there is the 150MW Aurora solar tower with eight hours of storage from molten salt, and a new pumped hydro storage project called Goat Hill has also emerged.

In Whyalla, the owner of the steelworks his proposing 1GW of solar, battery storage, pumped hydro, demand management and co-generation in a dramatic transformation of the way heavy industry sources energy in Australia.

CEFC wind sector lead Andrew Gardner said large-scale battery technology is developing rapidly, and it expects the costs of battery storage to fall significant, just as happened with wind and solar.

“This is the first development project in Australia which has been able to secure debt finance for a grid-connected large-scale battery component on a non-subsidised basis,” Garnder said.

“It provides an important financing model for other developers and investors wanting to be at the forefront of closer integration of renewables into the grid.”

He quoted Bloomberg New Energy Finance (BNEF) forecasts that Australia will have more than 29,000MW of flexible capacity installed by 2040, including both large-scale and small-scale batteries and demand response capability

He said this growth will support better management of variable generation as lower cost renewables become an increasingly important part of the electricity mix.

The CEFC said the combination of batteries at Lincoln Gap, Hornsdale and  Wattle Point will provide a significant amount of frequency response services to the South Australian grid.

The Lincoln Gap project is expected to be operational from mid-2018.

It has secured two long term Large Scale Generation Certificate (LGC) agreements with ERM Power and a long-term electricity offtake agreement with Snowy Hydro, but it is also reserving a significant share of its output for the merchant market.

Zeki Akbas from Nexif Energy Australia said “bundled” contracts – where developers of wind or solar projects deliver all the LGCs and output to a single retailer – were not doing great favours to wind farm developers.

Construction of the wind farm, 15 kilometres west of the Spencer Gulf town of Port Augusta, was expected to begin by the end of November and both the wind farm and the battery storage should be in place by the end of 2018.

“We are pleased to include grid-scale battery storage as an essential part of the wind farm investment and were happy to receive strong support and encouragement from the CEFC as our investment partner,” he said in a statement.

“With the scalable battery storage at Lincoln Gap we will be able to offer more flexibility to the national grid and improve the reliability of the system.”

The Lincoln Gap wind farm will feature  Senvion 3.6M140 EBC turbines, which are designed for moderate and strong wind speeds to enable optimised load management even in challenging wind conditions.

 The project has signed a contract for the delivery of large scale renewable energy certificates to ERM, and a long term electricity output contract with Snowy Hydro. Investec has also contributed around $40 million of finance.

CEFC recently made a $94 million investment in Australia’s first fully integrated wind, solar and battery project, at the Queensland Kennedy Energy Park.

Gardner said he expected investors will be increasingly attracted to such large-scale hybrid renewable energy projects as the next wave of investment and technological innovation.

“By financing these integrated generation and storage projects, the CEFC is demonstrating how Australia can continue to increase our renewable energy capacity, while providing the important ancillary benefits necessary for grid stability and security.”

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Solar Insiders Podcast: Why new rules for networks signal a new dawn for consumers

AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…

17 July 2026

Developer lands “complete funding package” to begin building state’s largest solar-battery hybrid

Developer says it is good to go on early works and construction of the largest…

17 July 2026

“A really big game-changer:” AEMO looks to battery inverters as syncons prove expensive and hard to find

AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…

17 July 2026

Twiggy Forrest’s Squadron abandons plan for troubled New England wind farm

Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…

17 July 2026

Energy Insiders Podcast: Is Australia on target for a “step change” in energy?

AEMO’S head of systems Nicola Falcon on the 2026 ISP and the importance of grid…

17 July 2026

Australia’s solar PV recycling plans on hold after flagship pilot project suspended

Flagship pilot program to set up 100 sites around the country to collect used solar…

17 July 2026