Life after coal: Lincoln Gap wind farm powers up, battery to be installed soon

Published by

The former coal town of Port Augusta continues its transformation into a major renewable energy hub with the “powering up” of the 212MW Lincoln Gap wind farm, one of the biggest new developments in a state that already sources more than 50 per cent of its demand from wind and solar.

Lincoln Gap, about 12kms from Port Augusta, joins the 220MW Bungala solar farm, as two major clean energy replacements for the two coal fired generators – Northern and Playford – that dominated the city’s economy, and its environment – for decades.

The second stage of the Bungala facility is nearly finished, and more clean energy projects are planned for the town and its surrounding areas, including the 160MW Aurora solar tower and molten salt storage project, DP Energy’s huge wind and solar and storage project, and Sanjeev Gupta’s big battery associated with the “greening” of the Whyalla steelworks.

Singapore-based Nexif Energy says the successful “energisation” of the Lincoln Gap project’s major sub-station and associated network infrastructure is a major landmark and will enable the project to begin commissioning the first of the wind farm’s 59 Senvion turbines by August.

A 10MW/10MWh battery – provided by Fluence, which also built the Ballarat battery storage installation in Victoria and is signed up for a new solar and battery project in north Queensland, will be installed by the end of May, when it will begin the commissioning process.

Nexif has said it could double or triple the size of the battery project and is believed to be still considering its options. That will likely depend on the development of markets to recognise the capabilities of this and other batteries.

The remainder of the wind farm will be complete by the middle of the year.

Lincoln Gap has signed a long-term off take agreement with Snowy Hydro and will deliver large scale generation certificates to ERM Power, but will sell a significant portion into the open market. The project employs 110-140 people during construction, with more than half sourced from the local region.

The project is owned by Nexif Energy and funded by the Denham Capital and the Clean Energy Finance Corp.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Peter Dutton’s nuclear accounting trick #4: Assume climate change has no cost

What is omitted from the Coalition's nuclear policy costings is far more informative about the…

23 February 2025

Akaysha inks revenue swap deal for Queensland big battery with commodities trader

Akaysha Energy signs "sophisticated" revenue swap deal for its new Queensland big battery with a…

21 February 2025

Mount Isa turns to wind, solar and gravity storage to save city as big mines close

Mount Isa is looking to green energy and gravity storage in its disused mine shafts…

21 February 2025

Energy Insiders Podcast: Why is the green energy transition made to sound so hard?

Climate 200's Simon Holmes a Court on the upcoming election, the role of independents, lessons…

21 February 2025

Peter Dutton’s nuclear accounting trick #3: Hide the costs of keeping coal

The Coalition’s nuclear plan takes a gamble with our electricity system that old coal will…

21 February 2025

Indigenous-owned energy retailer branches further across NEM, supplies power to NBN

Australia's first Indigenous-owned energy retailer is expanding into two more states just eight months after…

21 February 2025