Wind

“Largest ever” turbine blades en route to Australia’s largest wind farm

Published by

Construction is underway on what will be – at least for a time – Australia’s largest wind farm.

Project developer AGL Energy said on Friday that the foundations had been laid at the site of the 453MW Coopers Gap Wind Farm in Queensland, and parts of the massive turbines were making their journey from port to site, around 180km north of Brisbane.

And when we say massive, we mean massive – as in, the largest wind turbine blades ever transported in Australia.

That’s according to AGL, who said a trial delivery of the blades and other components had been successfully completed on Tuesday, in preparation for “sustained overnight deliveries” for the rest of the year.

AGL Project Manager, Tim Knill, says the largest turbine blades measure 67.2 metres long and weigh in at a hefty 22 tonnes.

“Several shipments of wind farm components, including the blades, have arrived at the Port of Brisbane and are in storage awaiting transportation,”  Knill said.

“The movement of such large pieces of equipment requires detailed planning and we are predicting approximately 1,200 oversize movements, involving blades, hubs, tower sections and nacelles,” he said.

“We aim to minimise the impacts on commuters so many of the movements are done at night time.”

Knill says the increased level of complexity of transporting the extra long blades is compensated for by the fact that, once installed, they allow more energy to be captured by every turbine, thus bringing down the cost of generation.

On that matter, Coopers Gap has already impressed, having secured – in August last year – an off-take price of below $60/MWh for energy generated by the south-east Queensland wind farm.

The deal included AGL writing a PPA for electricity and associated renewable energy certificates of less than $60/MWh for an initial five years, with an option to extend the agreement for another five years at the same – or even lower – price.

Once completed – it’s expected to be operational by mid-2019 — the project will comprise a total of 123 wind turbines, with 91 x 3.63MW turbines (137m rotor diameter) and 32 x 3.83MW (130m rotor diameter) turbines.

“The wind turbines will have a tip height of 180 metres. The hub height (axis or rotation) will be 110 metres (3.6MW – 137) or 115 metres (3.8MW – 130),” said Knill.

“The total capacity of the wind farm will be 453MW making it the largest wind farm by MW capacity in Australia.

“It’s estimated around $56 million will be spent by the project on services provided by local businesses during the construction phase… with 20 ongoing jobs created on site to maintain and operate the turbines.”

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

AEMO reports surge in grid registrations for wind, solar and battery projects

The rate of grid registrations for wind, solar and battery projects has surged in the…

11 February 2025

High winds detach another serrated edge from turbine at Australia’s largest wind project

Heavy winds detach another piece of serrated edging from a turbine at the country's biggest…

10 February 2025

Australia’s oldest commercial wind farm to close as cost of repowering is too high

Australia's oldest commercial wind farm will be decommissioned in 2027 as it owner says the…

10 February 2025

Flexible exports and solar soaks: Network shoots for “flat bills” as electrification era takes off

AusNet seeks approval to spend $3.5bn on upgrading its network over a five-year period it…

10 February 2025

Australia formally misses UN climate deadline, only one country makes pledge close to 1.5°C

Australia, as expected, has missed the official but largely symbolic deadline for its 2035 emissions…

10 February 2025

“Freedom from blackmail:” Baltic states cut their link to Russia grid in dramatic switch to EU network

Workers cut transmission lines to Russia grid and hand out chopped wire to bystanders in…

10 February 2025