Lal Lal wind farm’s Yendon section now connected to Victoria grid

Published by

Part of the massive Victorian wind farm that will help supply Australian packaging giant Orora with 80 per cent wind-generated renewable energy is now sending power to the grid.

As illustrated in the chart below, provided by Paul McArdle from Watt Clarity, the Yendon section of Maquarie Capital’s 228MW Lal Lal wind farm connected to the National Electricity Market mid-way through June.

The project, originally developed by WestWind Energy and then sold to Macquarie Capital in May 2017, is located south-east of Ballarat on two sections of farmland in the Moorabool Shire: the Yendon Section (2km east of Yendon) and the Elaine Section (2km north of Elaine).

The project reached financial close in mid-2018, when Macquarie solar two 40 per cent equity stakes in the project – one each to InfraRed Capital Partners and Northleaf Capital Partners.

News of the PPA with Orora quickly followed – a deal that, according to Macquarie, had allowed the packaging company to “lock in the cost of attaining baseload green energy.”

The 10-year agreement also includes a Proxy Revenue Swap (PRS), to help offset any production volume, timing of energy generation and future energy price risks – a first for the Australian renewables sector.

For Orora, which spun out of Amcor in 2013, the shift to clean energy started in February off 2018, when the company signed an agreement with Pacific Hydro to see all of its South Australia energy requirements met, 24/7, by the Clements Gap Wind Farm.

The rest of Lal Lal, which is being built through a joint venture between Zenviron and Vestas, is expected to be completed by the end of 2019.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: ppa

Recent Posts

New 1660 MWh battery reaches full output on time and under budget, but it may soon have a new owner

One of the biggest batteries in Australia's main grid reaches full output, as its owner's…

2 June 2026

Wind farm breathes life into local manufacturing as last of 69 massive steel cages are sent to site

Three Australian companies have helped deliver the last of the foundations of the only wind…

2 June 2026

Stop taxing the transition: Why fixed network charges get consumer energy resources all wrong

High fixed network tariffs lock in legacy cost structures, and protects the network's revenue position…

2 June 2026

Huge 10-hour battery attracts big wad of long distance objections, joins federal green queue

"Evil, poisonous and treacherous" was the description from one Queenslander about the central NSW battery…

2 June 2026

Spot prices along the journey to a competitively priced coal-free grid. But we still need a lot of wind

Australia will have a globally competitive electricity price in a no-coal world. It just needs…

2 June 2026

Illegal use of plug-in batteries adds urgency to campaign to approve balcony solar

A handful of Australians are already plugging in portable home batteries – illegally – suggesting…

2 June 2026