Kidston Solar Project reaches Practical Completion

Published by

PRESS RELEASE

Genex Power Limited (ASX: GNX) (Genex or Company) is pleased to announce that its 50MW Kidston Solar Project (KS1 or Project) has successfully reached Practical Completion (PC).
PC marks the final milestone of the construction and commissioning stages of the Project. Following energisation in late 2017, the Project has undergone detailed commissioning processes that have allowed for the gradual ramp-up to full capacity. Engineering, Procurement and Construction (EPC) contractor UGL has successfully passed all the commissioning and performance tests required for PC to be granted.
The Project will continue to be operated and maintained by UGL under the terms of an Operation and Maintenance (O&M) Agreement for an initial 5-year period, with an option for Genex to extend for an additional 5 years.
Commenting on the final milestone, Chief Executive Officer of Genex, James Harding stated:
“We are very pleased to have successfully reached Practical Completion for KS1. This marks the completion of the Project construction and commissioning phase, and is the culmination of a successful cooperation between Genex, UGL, Ergon Energy and the Australian Energy Market Operator. We wish to thank UGL for their professionalism and efforts to finalise the Project and complete the outstanding EPC components, and we look forward to continuing our collaboration during the O&M phase.”
About Genex Power Limited:
Genex Power is a power generation development company listed on the ASX. The Company is focused on innovative clean energy generation and electricity storage solutions which deliver attractive commercial returns for shareholders. The Company has a development pipeline of up to 770MW of renewable energy generation and storage projects within its portfolio, underpinned by the Kidston Renewable Energy Hub in far-north Queensland (Kidston Hub). The Kidston Hub is comprised of the operating 50MW Stage 1 Solar Project (KS1), the 250MW Pumped Storage Hydro Project (K2-Hydro) and the multi-staged integrated Solar Project of up to 270MW (K2-Solar) under development and the Kidston Stage 3 Wind Project of up to 150MW under feasibility. In addition, the Company has acquired the 50MW Jemalong Solar Project (JSP), located near Forbes in NSW, which is also under development.
Genex continues to acknowledge the support from the Federal Government, through the Australian Renewable Energy Agency (ARENA), which provided $8.9 million in funding to support the construction of the KS1 Project, in addition to their support of up to $9 million in funding to support the development of the stage 2 projects. Genex also acknowledges the support of the Queensland State Government through providing a 20-year revenue support deed and designating the Hub as ‘Critical Infrastructure’ to the State.
Share
Published by

Recent Posts

Australia urged to look west to tap into green iron boom and up to $400 billion of annual exports

Australia could almost quadruple the value of its iron ore exports by turning the mineral…

30 November 2026

Australia’s green energy transition in limbo as Victoria Labor crushed by right-wing political forces

Updated: The thumping triumph of right wing parties over Labor in Victoria puts the state's…

29 November 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

Passing of a solar legend, moves at OptiGrid, KordaMentha, and Mojo, and new CEOs for…

29 November 2026

Solar Insiders Podcast: The “electric jerry can” bridging the gap to plug-in batteries

Brad Davis from Clutch Industries on how the Arena-backed Melbourne company is using solid-state batteries…

27 November 2026

Coalition under fire over 11th-hour plan to gut and starve SEC, and sell its wind, solar and storage assets

Coalition leader unveils last minute pledge to sell off the renewables assets of the State…

27 November 2026

Chart of the Day: The evolution of the home battery boom – and signs of market distress

The latest quarterly CER update is the first with all three months under the Cheaper…

27 November 2026