Renewables

Kidston pumped hydro storage capacity to be boosted by 25%

Published by

Genex Power’s world-leading solar and pumped hydro project in northern Queensland looks set to provide 25 per cent more energy storage capacity than first thought, after an optimisation study showed the potential for the renewable energy hub to provide 8 hours of continuous generation, rather than six hours.

Genex Power’s $330 million Kidston Stage 2 Pumped Hydro Storage project – which is said to be “shovel ready” at the site of a former gold mine, where it will be co-located alongside a 270MW solar PV array – was initially slated to provide 1,500MWh of pumped hydro energy storage capacity.

But in a statement on Friday, Genex said that new studies had shown that it could provide energy storage of 2000MWh, with optimal use of the site’s existing infrastructure and design of its turbine technology.

The company said its optimisation studies, conducted with global engineering firm Mott MacDonald, had also taken into account recent shifts in Australian energy market dynamics, as well as feedback from key market players – the company is said to be close to announcing which major energy retailer will be the energy off-take partner for Kidston, with financial close set for 2018.

“It is clear that the National Electricity Market is undergoing a rapid shift from a traditional baseload dominant market to a new dynamic where dispatchability and storage of renewable energy will underpin future generation,” Genex said in a statement on Friday.

“In such a system, the role of large-scale economic energy storage becomes increasingly relevant.

“The updated design (of Kidston) will enable energy off-takers to take full advantage of the flexibility offered by the integrated project and, in doing so, allow Genex to extract maximum value from the offtake arrangements.”

The optimisation study, says Genex, found that an augmented design using the two existing gold mine pits as the upper and lower reservoirs was the optimal choice for the 250MW of installed solar capacity.

This change was expected to increase upper reservoir volume from six hours to over eight hours of continuous generation, with the potential to use variable speed pump-generator turbines to provide significant operational flexibility, including the ability to “ramp up” to full generation capacity in less than 30 seconds.

The changes would also allow the pumped hydro facility to better match the generation from the co-located K2-Solar project, Genex said, as well as increasing its suitability to the ancillary service market with increased operation flexibility.

As a final bonus, the reduced excavation and civil works requirements that result from the optimisation means construction of the pumped hydro project could be reduced by up to six months, to less than three years, the company said.

“The optimisation study outcomes have been developed in response to direct feedback from potential energy partners amid the ongoing backdrop of the national debate on Energy Policy, and the importance of ensuring dispatchability of renewable energy via energy storage,” said Genex managing director Michael Addison in comments on Friday.

“The Kidston renewable energy hub is currently the most advanced, lowest cost, large-scale energy storage project in the country. Energy storage is likely to play a critical role in future energy
development and Genex is well placed to benefit from these dynamics,” he said.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Massive methane cloud spotted over massive Australian oil and gas project blamed on faulty CCS system

One of the world's largest oil and gas projects located in Australia vented dangerous plumes…

25 November 2026

Approval sought for one of Australia’s biggest wind, solar and battery parks in Queensland coal region

Approval sought for a massive wind, solar and battery project to be located in the…

25 November 2026

“Heat pumps don’t work well in alpine areas:” Gas lobby continues war on electricity with wild claims at industry debate

Misinformation, debunked myths repeated as truth, and jaw-dropping misdirection al featured in a fiery debate…

25 November 2026

The fossil fuel-backed IPA’s deep connections with likely new Liberal premier

The likely new premier of Victoria, and her closest advisors, have deep connections with fossil…

25 November 2026

“Never seen volatility like this:” Solar veteran says industry in crisis due to home battery glut and policy swings

Supply gluts and policy swings causing crisis in home solar and battery market, with deep…

25 November 2026

Chinese energy giant signs up for 400 MW green hydrogen system to make iron and steel in NSW

Builder of world's first zero emissions industrial park brought in help design a 400 MW…

25 November 2026