The island’s administrator and council have become the first to use new rules that allow network spending decisions to be challenged by local communities. They say the decision lacks transparency and they want a review – and they are questioning the whole process.
Some of the island’s residents had hoped to convince the network operator to junk plans to replace the ageing cable that links the island to the main grid, and instead support a home-grown renewable energy plan to enable the island to use renewables – wind, solar and biomass – to meet its own electricity needs.
It was a project, its proponents said, that could pioneer a new age of renewable energy, on what was the country’s first free-settled colony.
That plan, however, came undone after South Australia Power Networks revealed that the cost of replacing the cable would only come to around half of its previous estimates ($25.6 million versus $45.6 million). That undercut the 100% renewable energy plan.
But SAPN earned the islanders’ wrath when it decided on a new 33kv cable to the island, rather than a 66kv cable that could carry more capacity.
The Kangaroo Island community wants a 66kv cable installed, noting it would cost just $1.9 million more, would ensure that all future needs are met, and offer an opportunity to export power back to the mainland.
As a result, the Commissioner for Kangaroo Island and the Kangaroo Island Council have lodged a formal “dispute notice” to the Australian Energy Regulator, the first time a Regulatory Investment Test has been disputed.
“This piece of crucial infrastructure must be able to provide for growth in demand for electricity on Kangaroo Island and for the island’s potential to harness its natural resources and export energy back to the rest of South Australia,” mayor Peter Clements says.
The islanders want to keep their options open – they have vast swathes of eucalyptus plantings that could generate biomass power, not to mention excellent wind resources – and also question if SAPN has taken into account nearly $200 million of new developments.
Wendy Campana, the island’s commissioner, says the community is questioning the whole process, and why SAPN originally described the best option as a 66kV cable that would cost around $45 million, when they ended up settling on a cable with half the capacity and half the price.
According to advice it has received, the commission suspects that the network owner will get a “bonus” of around $10 million for having found a “cheaper option”.
“We are actually questioning why it can go to submissions, and say 66kV and $45 million, (then say) we only need 33kV and $25 million. They get to keep the difference.”
Campana says that if it was clear that the cable would cost around $25 million, then proponents of competing options, including those of high renewables, might have been able to better tailor other options.
As it is, one of the proponents of the 100 per cent renewable energy plan, the Sydney-based Institute for Sustainable Futures, is regretting the decision, saying that there was an opportunity for a mix of wind, solar, storage and biomass that could have looked after the island’s needs.
However, ISF’s Chris Dunstan says it was a difficult plan to pursue without the enthusiastic support of a majority of the island community. “It seems like a lost opportunity,” he says.
Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…
Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…
In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…
In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…
CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…
Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…