Kaban wind farm powers up, connects to Queensland’s renewable “SuperGrid”

Published by

Neoen Australia’s 157MW Kaban wind farm has officially connected to Queensland’s “SuperGrid,” the state’s grand new name for the beefed up electricity network that will need to accommodate 80% renewables by 2035.

The wind farm – which is said to be at the half-way mark of construction, with 16 of its 28 Vestas V162-5.6MW EnVentus turbines fully installed – was energised on Tuesday.

The project is part of Neoen Australia’s Green Power Hub, which has plans to add a big battery, and will take in a 320km transmission line upgrade of the coastal circuit from Cairns to Townsville.

The Queensland government’s green energy utility, CleanCo, has signed a 15-year offtake deal to purchase 100 per cent of the output from the wind farm.

Deputy Premier Steven Miles on Tuesday marked the project as the first for the Sunshine State’s first renewable energy zone, the Northern Queensland REZ.

“This project is perfectly positioned to capitalise on the world-renowned wind resources of Northern Queensland,” Miles said.

The milestone for the Neoen project comes less than a week after the Palaszczuk government announced ambitious new renewable energy targets, including 70% by 2032 and 80% by 2035.

Queensland Labor’s new plans aim to add 22GW of new wind and solar, 11.5GW of rooftop solar, 9GW of battery storage and 7GW of pumped hydro storage to a renewable energy SuperGrid, most of it over the coming decade.

The state’s minister for energy, renewables and hydrogen Mick de Brenni said on Tuesday that the government’s $700 million investment in the North Queensland transmission network over the next five years aims to keep the new renewables generation flowing.

“This new transmission infrastructure will be delivered by Powerlink and will unlock an additional 500MW of renewables capacity in the region,” de Brenni said at an event for the Kaban wind farm in the Tablelands.

“Projects like this enable the cost-effective connection of multiple renewable energy developments into the network, making it easier to bring more clean energy to enter the system.”

Neoen managing director Louis de Sambucy said the company was proud of Kaban’s role as the cornerstone project of Queensland’s first renewable energy zone.

“I’d like to thank the Queensland government and CleanCo for their vision and support, and Powerlink for their hard work and commitment in delivering the essential transmission infrastructure,” he said.

Queensland Premier Annastacia Palaszczuk says the energisation of Kaban signifies the first injection of clean energy into the new Queensland SuperGrid.

“Once complete early next year, [the wind farm] will generate 460,000MW hours of clean energy a year, enough to power up to 100,000 homes,” the premier said.

The project is also noted for its huge turbines, which from the base of the tower to the highest tip of the blade reach 230 metres into the air.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“Serious impact:” Budget home battery brand faces suspension from rebate due to non-compliance

Seven home battery models from one of the up and coming new budget brands on…

8 September 2026

Rock lobsters and whales: First offshore wind project on west coast hits the EPBC queue

French energy giant seeks federal approval to start work on offshore wind projects in newly…

8 September 2026

New pumped hydro project seeks approval in New England, but already faces local opposition

Proposed pumped hydro project in New England plans 300 MW of capacity and 10 hours…

8 September 2026

“It’s an ideology:” Queensland LNP accused of deliberate strategy to kill large scale renewables

Updated. Queensland :NP accused of having deliberate policy to make renewable uninvestable by scrapping targets,…

8 September 2026

Renewables lobby says coal generators should pay carbon price to stay open beyond stated closure dates

Smart Energy Council calls for a carbon price to be imposed on coal fired power…

8 September 2026

Biggest ever battery project – up to 4,800 megawatt hours – seeks federal and state planning approvals

State and federal planning permits sought for what could be the biggest battery project in…

7 September 2026